Commission of the European Communities v Italian Republic. (Approximation of laws) [1993] EUECJ C-107/92 (2 August 1993)

Commission of the European Communities v Italian Republic. (Approximation of laws) [1993] EUECJ C-107/92 (2 August 1993)

Italy did not demonstrate the existence of extreme urgency within the meaning of Article 9(d) of the Directive, as there was sufficient time to comply with the accelerated procedure for advertising the contract.

Source-derived case information.

Citation
[1993] EUECJ C-107/92
Parties
Applicant: Commission of the European Communities; Respondent: Italian Republic
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings Under Article 169 EEC Treaty / Final Judgment
Outcome
Declaration of failure to fulfil obligations; order to pay costs
Legal Topics
Failure to Fulfil Obligations, Public Works Contracts, Advertising Requirements, Derogation for Urgency
European Union Law Public Procurement Failure to Fulfil Obligations Public Works Contracts Advertising Requirements Derogation for Urgency

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Commission of the European Communities

Applicant

Italian Republic

Respondent

Procedural Posture

Infringement Proceedings Under Article 169 EEC Treaty / Final Judgment

  1. 1 Whether Italy failed to fulfil its obligations under Directive 71/305/EEC by not publishing a contract notice for public works in the Official Journal
  2. 2 Whether the derogation for extreme urgency under Article 9(d) of the Directive applied

Ratio Decidendi

Italy did not demonstrate the existence of extreme urgency within the meaning of Article 9(d) of the Directive, as there was sufficient time to comply with the accelerated procedure for advertising the contract.

Court Disposition

Declaration of failure to fulfil obligations; order to pay costs

Orders

  • Italian Republic failed to fulfil its obligations under Directive 71/305/EEC by not publishing a contract notice for the avalanche barrier project.
  • Italian Republic is ordered to pay the costs.