Commission of the European Communities v Italian Republic. (Member States) [1993] EUECJ C-139/92 (2 August 1993)

Commission of the European Communities v Italian Republic. (Member States) [1993] EUECJ C-139/92 (2 August 1993)

Italy failed to fulfil its obligations under Articles 8 and 9 of Directive 83/189/EEC by not communicating Ministerial Decree No 514 at the draft stage.

Source-derived case information.

Citation
[1993] EUECJ C-139/92
Parties
Applicant: Commission of the European Communities; Respondent: Italian Republic
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings / Final Judgment
Outcome
declaration of failure to fulfil obligations; costs awarded against Italy
Legal Topics
Failure to Fulfil Obligations, Technical Standards, Notification Procedures
European Union Law Administrative Law Failure to Fulfil Obligations Technical Standards Notification Procedures

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Commission of the European Communities

Applicant

Italian Republic

Respondent

Procedural Posture

Infringement Proceedings / Final Judgment

  1. 1 Whether Italy failed to communicate Ministerial Decree No 514 at the draft stage as required by Directive 83/189/EEC
  2. 2 Whether this failure constitutes a breach of Articles 8 and 9 of Directive 83/189/EEC

Ratio Decidendi

Italy failed to fulfil its obligations under Articles 8 and 9 of Directive 83/189/EEC by not communicating Ministerial Decree No 514 at the draft stage.

Court Disposition

declaration of failure to fulfil obligations; costs awarded against Italy

Orders

  • Declares that Italy failed to fulfil its obligations under Articles 8 and 9 of Directive 83/189/EEC by not communicating Ministerial Decree No 514 at the draft stage.
  • Orders the Italian Republic to pay the costs.