Commission v Belgium (Industrial policy) [2002] EUECJ C-221/01 (19 September 2002)

Commission v Belgium (Industrial policy) [2002] EUECJ C-221/01 (19 September 2002)

Belgium failed to implement mechanisms for monitoring compliance with cost accounting systems, did not provide regulatory authorities with specific powers to intervene in interconnection negotiations at any time, and did not ensure proper publication of the main elements of the national numbering plan as required by...

Source-derived case information.

Citation
[2002] EUECJ C-221/01
Parties
Applicant: Commission of the European Communities; Respondent: Kingdom of Belgium
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings Under Article 226 EC / Final Judgment
Outcome
Application upheld in part; Belgium found in breach of obligations under Directive 97/33/EC.
Legal Topics
Implementation of EU Directives, Universal Service, Interconnection Agreements, Regulatory Authority Powers, Publication Requirements
European Union Law Telecommunications Law Implementation of EU Directives Universal Service Interconnection Agreements Regulatory Authority Powers Publication Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2
Sign in to unlock

Parties

Commission of the European Communities

Applicant

Kingdom of Belgium

Respondent

Procedural Posture

Infringement Proceedings Under Article 226 EC / Final Judgment

  1. 1 Whether Belgium failed to implement Articles 7(5), 9(3), and 14(1) in conjunction with Article 12(4) of Directive 97/33/EC

Ratio Decidendi

Belgium failed to implement mechanisms for monitoring compliance with cost accounting systems, did not provide regulatory authorities with specific powers to intervene in interconnection negotiations at any time, and did not ensure proper publication of the main elements of the national numbering plan as required by Directive 97/33/EC.

Court Disposition

Application upheld in part; Belgium found in breach of obligations under Directive 97/33/EC.

Orders

  • Belgium declared to have failed to fulfil obligations under Articles 7(5), 9(3), and 14(1) in conjunction with Article 12(4) of Directive 97/33/EC.
  • Belgium ordered to pay the costs.