Commission v Austria (Environment and consumers) [2005] EUECJ C-15/03 (27 January 2005)

Commission v Austria (Environment and consumers) [2005] EUECJ C-15/03 (27 January 2005)

Austria failed to fulfil its obligations under Article 3(1) of Directive 75/439/EEC by not adopting measures necessary to give priority to the processing of waste oils by regeneration where technical, economic and organisational constraints so allow. The national legislation placed regeneration and combustion on the...

Source-derived case information.

Citation
[2005] EUECJ C-15/03
Parties
Applicant: Commission of the European Communities; Respondent: Republic of Austria; Intervener: Republic of Finland; Intervener: United Kingdom of Great Britain and Northern Ireland
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings / Final Judgment
Outcome
Application granted. Austria found in breach of obligations.
Legal Topics
Waste Management, Waste Oil Regeneration, Implementation of EU Directives, Member State Obligations
European Union Law Environmental Law Waste Management Waste Oil Regeneration Implementation of EU Directives Member State Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Commission of the European Communities

Applicant

Republic of Austria

Respondent

Republic of Finland

Intervener

United Kingdom of Great Britain and Northern Ireland

Intervener

Procedural Posture

Infringement Proceedings / Final Judgment

  1. 1 Whether Austria failed to give priority to the processing of waste oils by regeneration as required by Article 3(1) of Directive 75/439/EEC, as amended.

Ratio Decidendi

Austria failed to fulfil its obligations under Article 3(1) of Directive 75/439/EEC by not adopting measures necessary to give priority to the processing of waste oils by regeneration where technical, economic and organisational constraints so allow. The national legislation placed regeneration and combustion on the same footing, contrary to the Directive's required order of precedence.

Court Disposition

Application granted. Austria found in breach of obligations.

Orders

  • Austria declared to have failed to fulfil its obligations under Article 3(1) of Directive 75/439/EEC as amended.