Commission v United Kingdom (Environment & consumers) [2006] EUECJ C-138/06 (14 December 2006)
The United Kingdom failed to adopt, within the prescribed period, the laws, regulations and administrative provisions necessary to comply with Directive 2002/49/EC, thereby failing to fulfil its obligations under that directive.
Source-derived case information.
- Citation
- [2006] EUECJ C-138/06
- Parties
- Applicant: Commission of the European Communities; Respondent: United Kingdom of Great Britain and Northern Ireland
- Jurisdiction
- European Union
- Procedural Posture
- Infringement Proceedings / Final Judgment
- Outcome
- Application granted
- Legal Topics
- Failure to Transpose EU Directive, Environmental Noise Management, Member State Obligations
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Commission of the European Communities
Applicant
United Kingdom of Great Britain and Northern Ireland
Respondent
Procedural Posture
Infringement Proceedings / Final Judgment
Legal Issues
- 1 Whether the United Kingdom failed to adopt the necessary laws, regulations and administrative provisions to comply with Directive 2002/49/EC within the prescribed period
Ratio Decidendi
The United Kingdom failed to adopt, within the prescribed period, the laws, regulations and administrative provisions necessary to comply with Directive 2002/49/EC, thereby failing to fulfil its obligations under that directive.
Court Disposition
Application granted
Orders
- It is declared that the United Kingdom failed to fulfil its obligations under Directive 2002/49/EC by not adopting the necessary measures within the prescribed period.
- The United Kingdom is ordered to pay the costs.
Full Case Text
Judgment text and source record
1 paragraphs
Judgment 1 By its application, the Commission of the European Communities seeks a declaration from the Court that, by failing to adopt the laws, regulations and administrative provisions necessary to comply with Directive 2002/49/EC of the European Parliament and of the Council of 25 June 2002 relating to the assessment and management of environmental noise (OJ 2002 L 189, p. 12; -�the Directive'), or, in any event, by not informing the Commission of those provisions, the United Kingdom of Great Britain and Northern Ireland has failed to fulfil its obligations under that directive. 2 The first subparagraph of Article 14(1) of the Directive provides that the Member States were to bring into force the laws, regulations and administrative provisions necessary to comply therewith no later than 18 July 2004 and to inform the Commission thereof. 3 Having sent, on 15 December 2004, a letter of formal notice to the United Kingdom, the Commission, on 13 July 2005, issued a reasoned opinion in which it concluded that, by omitting to adopt the laws, regulations and administrative provisions necessary for the transposition of the Directive into its national law, that Member State had infringed its obligations under that directive. The Commission also requested the United Kingdom to adopt the measures necessary to comply with that reasoned opinion within a period of two months from its notification. 4 The United Kingdom authorities replied to that opinion by a letter of 13 September 2005, indicating the state of progress of the transposition of the Directive in England, Scotland, Wales and Gibraltar. 5 Since it received no further information enabling it to conclude that the provisions intended to effect the full transposition of the Directive in the United Kingdom had been adopted within the prescribed period, the Commission brought this action. 6 The United Kingdom Government admits that the Directive was not transposed within the prescribed period, but states that the laws and regulations intended to effect such transposition should have been adopted, at the latest, during November 2006 7 It follows from the Court's settled case-'law that the question whether a Member State has failed to fulfil its obligations must be determined by reference to the situation obtaining in the Member State at the end of the period laid down in the reasoned opinion and the Court cannot take account of any subsequent changes (see, in particular, Case C-'394/00 Commission v Ireland [2002] ECR I-'581, paragraph 12, and Case C-'428/04 Commission v Austria [2006] ECR I-'3325, paragraph 38). 8 In this case, it is common ground that, on the expiry of the period of two months laid down in the reasoned opinion, the measures necessary to effect the Directive's transposition into law in the United Kingdom had not been adopted. 9 In those circumstances, the Commission's action must be held to be well founded. 10 Therefore, it must be declared that, by failing to adopt, within the prescribed period, the laws, regulations and administrative provisions necessary to comply with the Directive, the United Kingdom has failed to fulfil its obligations under that directive. Costs 11 Under Article 69(2) of the Rules of Procedure, the unsuccessful party is to be ordered to pay the costs, if they have been applied for in the successful party's pleadings. Since the Commission has applied for costs and the United Kingdom has been unsuccessful in its pleas in law, the United Kingdom must be ordered to pay the costs. On those grounds, the Court (Fifth Chamber) hereby: 1. Declares that, by failing to adopt, within the prescribed period, the laws, regulations and administrative provisions necessary to comply with Directive 2002/49/EC of the European Parliament and of the Council of 25 June 2002 relating to the assessment and management of environmental noise, the United Kingdom of Great Britain and Northern Ireland has failed to fulfil its obligations under that directive; 2. Orders the United Kingdom of Great Britain and Northern Ireland to pay the costs. [Signatures] * Language of the case: English. BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII