Parliament v SERS and Ville de Strasbourg (Law governing the institutions) [2003] EUECJ C-167/99 (10 April 2003)

Parliament v SERS and Ville de Strasbourg (Law governing the institutions) [2003] EUECJ C-167/99 (10 April 2003)

The Court held that the Parliament's application was admissible as the time limit was suspended by the internal transmission between courts. The counterclaim by SERS and the City was also admissible as it was filed within the procedural time limit. On the merits, the Court found that the contractual completion date...

Source-derived case information.

Citation
[2003] EUECJ C-167/99
Parties
Applicant: European Parliament; Respondent: Société d'aménagement et d'équipement de la Région de Strasbourg (SERS); Respondent: Ville de Strasbourg (City of Strasbourg)
Jurisdiction
European Union
Procedural Posture
Contractual Dispute (ecj) / Final Judgment
Outcome
Application by the European Parliament allowed in part; counterclaim by SERS and the City dismissed; penalties for delay and exemption from interim interest confirmed as per contract interpretation.
Legal Topics
Jurisdiction of the Court of Justice, Interpretation of Contract Terms, Penalties for Delay, Force Majeure, Interim Interest, Admissibility of Claims and Counterclaims
European Union Law Contract Law Civil Procedure Jurisdiction of the Court of Justice Interpretation of Contract Terms Penalties for Delay Force Majeure Interim Interest +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 7 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

European Parliament

Applicant

Société d'aménagement et d'équipement de la Région de Strasbourg (SERS)

Respondent

Ville de Strasbourg (City of Strasbourg)

Respondent

Procedural Posture

Contractual Dispute (ecj) / Final Judgment

  1. 1 Whether the application by the European Parliament was admissible given the procedural transmission between courts and time limits
  2. 2 Whether the counterclaim by SERS and the City was admissible
  3. 3 Interpretation of the contractual completion date and grounds for extension under the framework contract

Ratio Decidendi

The Court held that the Parliament's application was admissible as the time limit was suspended by the internal transmission between courts. The counterclaim by SERS and the City was also admissible as it was filed within the procedural time limit. On the merits, the Court found that the contractual completion date was 31 December 1997, extendable only for grounds specified in clause 5.2 of the framework contract. Penalties for delay were due automatically if that date, as extended by justified grounds, was exceeded. The Court rejected the respondents' argument that the date was merely estimated and held that the Parliament was entitled to penalties for delay and exemption from interim...

Court Disposition

Application by the European Parliament allowed in part; counterclaim by SERS and the City dismissed; penalties for delay and exemption from interim interest confirmed as per contract interpretation.

Orders

  • The Parliament's application is admissible.
  • The counterclaim by SERS and the City is admissible but dismissed on the merits.