Fulvio Fonzi v Commission de la CEEA. [1965] EUECJ C-28/65R (7 July 1965)

Fulvio Fonzi v Commission de la CEEA. [1965] EUECJ C-28/65R (7 July 1965)

The applicant failed to prove the urgency required for suspension of the Commission's decision, especially given the delay between the decision and the application for interim relief. The grounds raised concern the substance of the main case and do not justify interim suspension.

Source-derived case information.

Citation
[1965] EUECJ C-28/65R
Parties
Applicant: Fulvio Fonzi; Defendant: Commission of the European Atomic Energy Community
Jurisdiction
European Union
Procedural Posture
Interim Application / Application for Suspension of Operation of Decision Pending Main Proceedings
Outcome
application for suspension dismissed
Legal Topics
Suspension of Administrative Decision, Powers of EU Institutions, Urgency in Interim Measures
European Union Law Administrative Law Suspension of Administrative Decision Powers of EU Institutions Urgency in Interim Measures

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Fulvio Fonzi

Applicant

Commission of the European Atomic Energy Community

Defendant

Procedural Posture

Interim Application / Application for Suspension of Operation of Decision Pending Main Proceedings

  1. 1 Whether the operation of the Commission's decision of 7 October 1964 should be suspended pending judgment in the main case
  2. 2 Whether the applicant demonstrated urgency justifying interim relief

Ratio Decidendi

The applicant failed to prove the urgency required for suspension of the Commission's decision, especially given the delay between the decision and the application for interim relief. The grounds raised concern the substance of the main case and do not justify interim suspension.

Court Disposition

application for suspension dismissed

Orders

  • The application to suspend the operation of the decision adopted on 7 October 1964 by the Commission of the European Atomic Energy Community with regard to the applicant is dismissed.
  • The costs are reserved.