Government of the Netherlands Antilles v Council of the European Union. (Association of the overseas countries and territories) [1998] EUECJ T-310/97 (2 March 1998)

Government of the Netherlands Antilles v Council of the European Union. (Association of the overseas countries and territories) [1998] EUECJ T-310/97 (2 March 1998)

The application for interim measures was refused because the applicant failed to demonstrate undeniable urgency or serious and irreparable damage, and the Council's assessment should not be overridden absent such urgency. The time-limit for mid-term review in Council Decision 91/482 is a guideline, not a strict...

Source-derived case information.

Citation
[1998] EUECJ T-310/97
Parties
Applicant: Government of the Netherlands Antilles; Respondent: Council of the European Union
Jurisdiction
European Union
Procedural Posture
Application for Interim Measures / Interlocutory Proceedings
Outcome
application for interim measures refused
Legal Topics
Interim Measures, Urgency, Association of Overseas Countries and Territories, Council Decision 91/482, Suspension of Operation of a Measure
European Union Law Administrative Law Interim Measures Urgency Association of Overseas Countries and Territories Council Decision 91/482 Suspension of Operation of a Measure

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Government of the Netherlands Antilles

Applicant

Council of the European Union

Respondent

Procedural Posture

Application for Interim Measures / Interlocutory Proceedings

  1. 1 Whether the application for interim measures meets the conditions of urgency and serious and irreparable damage
  2. 2 Whether the time-limit for mid-term review in Council Decision 91/482 is binding or a guideline

Ratio Decidendi

The application for interim measures was refused because the applicant failed to demonstrate undeniable urgency or serious and irreparable damage, and the Council's assessment should not be overridden absent such urgency. The time-limit for mid-term review in Council Decision 91/482 is a guideline, not a strict deadline.

Court Disposition

application for interim measures refused

Orders

  • The application for interim measures is dismissed.