Autonome Provinz Bozen (Aid granted by Member States - construction of mini-hydroelectric power plants - Alpine and mountain huts without connection - Judgment) [2022] EUECJ C-102/21 (07 April 2022)

Autonome Provinz Bozen (Aid granted by Member States - construction of mini-hydroelectric power plants - Alpine and mountain huts without connection - Judgment) [2022] EUECJ C-102/21 (07 April 2022)

Aid granted after expiry of Commission authorisation is unlawful and must be recovered by national authorities without Commission request; compatibility assessment is for the Commission, not national courts.

Source-derived case information.

Citation
[2022] EUECJ C-102/21
Parties
Applicant: KW; Applicant: SG; Respondent: Autonome Provinz Bozen (Autonomous Province of Bolzano, Italy)
Jurisdiction
European Union
Procedural Posture
Preliminary Reference / Judgment
Outcome
Questions answered; aid scheme authorisation expired; Commission not required to request recovery of unlawful aid; compatibility question inadmissible.
Legal Topics
State Aid Compatibility, Aid Recovery, Misuse of Aid, Unlawful Aid, Renewable Energy Subsidies
European Union Law State Aid State Aid Compatibility Aid Recovery Misuse of Aid Unlawful Aid Renewable Energy Subsidies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 12 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

KW

Applicant

SG

Applicant

Autonome Provinz Bozen (Autonomous Province of Bolzano, Italy)

Respondent

Procedural Posture

Preliminary Reference / Judgment

  1. 1 Whether Commission authorisation for aid scheme was in force when subsidies were granted
  2. 2 Whether Commission must request recovery of unlawful aid
  3. 3 Compatibility of aid with internal market under Article 107(3)(c) TFEU

Ratio Decidendi

Aid granted after expiry of Commission authorisation is unlawful and must be recovered by national authorities without Commission request; compatibility assessment is for the Commission, not national courts.

Court Disposition

Questions answered; aid scheme authorisation expired; Commission not required to request recovery of unlawful aid; compatibility question inadmissible.

Orders

  • National authorities must recover unlawful aid granted after expiry of authorisation.
  • Commission not required to request recovery of unlawful aid.