VAN HOUTEN v. THE NETHERLANDS - 25149/03 [2005] ECHR 659 (29 September 2005)

VAN HOUTEN v. THE NETHERLANDS - 25149/03 [2005] ECHR 659 (29 September 2005)

The Court accepted the Government's unilateral declaration acknowledging unreasonable duration, found the offered compensation reasonable, and decided it was no longer justified to continue examination of the application under Article 37 § 1 (c).

Source-derived case information.

Citation
[2005] ECHR 659
Parties
Applicant: Laurens Josephus van Houten; Respondent: Kingdom of the Netherlands
Jurisdiction
European Union
Procedural Posture
Application Under Article 34 ECHR / Striking Out Judgment
Outcome
Application struck out of the list
Legal Topics
Right to a Fair Trial, Reasonable Time for Proceedings, Just Satisfaction, Striking Out Applications
Human Rights Social Security Law Administrative Law Right to a Fair Trial Reasonable Time for Proceedings Just Satisfaction Striking Out Applications

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 11 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Laurens Josephus van Houten

Applicant

Kingdom of the Netherlands

Respondent

Procedural Posture

Application Under Article 34 ECHR / Striking Out Judgment

  1. 1 Whether the length of social-security proceedings violated Article 6 § 1 of the Convention
  2. 2 Whether the case should be struck out under Article 37 § 1 (c) of the Convention

Ratio Decidendi

The Court accepted the Government's unilateral declaration acknowledging unreasonable duration, found the offered compensation reasonable, and decided it was no longer justified to continue examination of the application under Article 37 § 1 (c).

Court Disposition

Application struck out of the list

Orders

  • Government to pay EUR 5,000 in respect of non-pecuniary damage and EUR 1,000 in respect of costs and expenses within three months; simple interest payable in case of default at ECB marginal lending rate plus three percentage points.