The Court held that while there was a delay in drawing up the staff report, the applicant failed to demonstrate actual compensable damage or a causal link between the delay and any alleged harm. The action for damages was therefore inadmissible and unfounded.

Source-derived case information.

Citation
[1997] EUECJ T-15/96
Parties
Applicant: Lino Liao; Respondent: Council of the European Union
Jurisdiction
European Union
Procedural Posture
Action for Annulment and Damages / Judgment
Outcome
action dismissed
Legal Topics
Officials, Staff Report, Delay, Actions for Annulment, Actions for Damages, Admissibility, Damage
European Union Law Employment Law Officials Staff Report Delay Actions for Annulment Actions for Damages Admissibility +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Lino Liao

Applicant

Council of the European Union

Respondent

Procedural Posture

Action for Annulment and Damages / Judgment

  1. 1 Whether the delay in drawing up the applicant's staff report constitutes a breach justifying annulment or damages
  2. 2 Whether the action for damages is admissible
  3. 3 Whether the applicant suffered compensable damage

Ratio Decidendi

The Court held that while there was a delay in drawing up the staff report, the applicant failed to demonstrate actual compensable damage or a causal link between the delay and any alleged harm. The action for damages was therefore inadmissible and unfounded.

Court Disposition

action dismissed

Orders

  • The action is dismissed.