MARPA ZEELAND B.V. AND METAL WELDING B.V. v. THE NETHERLANDS - 46300/99 [2004] ECHR 597 (9 November 2004)

MARPA ZEELAND B.V. AND METAL WELDING B.V. v. THE NETHERLANDS - 46300/99 [2004] ECHR 597 (9 November 2004)

Applicant companies were denied effective access to a court and meaningful exercise of their right of appeal due to improper persuasion by the Advocate General to withdraw appeals, and the length of proceedings was excessive, violating Article 6 § 1.

Source-derived case information.

Citation
[2004] ECHR 597
Parties
Applicant: Marpa Zeeland B. V.; Applicant: Metal Welding B. V.; Respondent: Kingdom of the Netherlands
Jurisdiction
European Union
Procedural Posture
Application to European Court of Human Rights / Final Judgment
Outcome
Violation of Article 6 § 1 found regarding fairness and length of proceedings.
Legal Topics
Right to Fair Trial, Reasonable Time Requirement, Access to Court, Remission of Sentence, Closed System of Legal Remedies
Criminal Law Human Rights Law Procedural Law Right to Fair Trial Reasonable Time Requirement Access to Court Remission of Sentence Closed System of Legal Remedies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 12 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Marpa Zeeland B. V.

Applicant

Metal Welding B. V.

Applicant

Kingdom of the Netherlands

Respondent

Procedural Posture

Application to European Court of Human Rights / Final Judgment

  1. 1 Whether the applicant companies were denied a fair hearing under Article 6 § 1 of the Convention
  2. 2 Whether the length of criminal proceedings against the applicant companies violated Article 6 § 1

Ratio Decidendi

Applicant companies were denied effective access to a court and meaningful exercise of their right of appeal due to improper persuasion by the Advocate General to withdraw appeals, and the length of proceedings was excessive, violating Article 6 § 1.

Court Disposition

Violation of Article 6 § 1 found regarding fairness and length of proceedings.

Orders

  • Respondent State to pay applicant companies EUR 7,000 for non-pecuniary damage and EUR 4,000 for costs and expenses within three months, plus any tax chargeable.
  • Simple interest payable on above amounts at marginal lending rate of European Central Bank plus three percentage points from expiry of three months until settlement.