Bisson v. Gibbins [1963] JJ 329 (20 November 1963)

Bisson v. Gibbins [1963] JJ 329 (20 November 1963)

A party suffering loss from breach of contract must take reasonable steps to mitigate that loss; failure to do so may limit recoverable damages.

Citation
[1963] JJ 329
Parties
Applicant: Bisson; Respondent: Gibbins
Jurisdiction
Jersey
Judgment Date
20 November 1963
Procedural Posture
Civil / Judgment
Outcome
judgment for applicant subject to mitigation principle
Legal Topics
Damages, Mitigation of Loss

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Bisson

Applicant

Gibbins

Respondent

Procedural Posture

Civil / Judgment

  1. 1 Whether a contracting party has a duty to mitigate loss after breach of contract

Ratio Decidendi

A party suffering loss from breach of contract must take reasonable steps to mitigate that loss; failure to do so may limit recoverable damages.

Court Disposition

judgment for applicant subject to mitigation principle