Fort v Le Claire [1994] JRC 091 (06 May 1994)

Fort v Le Claire [1994] JRC 091 (06 May 1994)

The court found that the respondent failed to perform contractual obligations, constituting a breach.

Citation
[1994] JRC 091
Parties
Applicant: Fort; Respondent: Le Claire
Jurisdiction
Jersey
Judgment Date
06 May 1994
Procedural Posture
Civil / Judgment
Outcome
judgment for applicant
Legal Topics
Breach of Contract

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Fort

Applicant

Le Claire

Respondent

Procedural Posture

Civil / Judgment

  1. 1 Whether the respondent breached the contract with the applicant

Ratio Decidendi

The court found that the respondent failed to perform contractual obligations, constituting a breach.

Court Disposition

judgment for applicant

Orders

  • Respondent to pay damages to applicant