Jersey Steel Co. v Holdyne Ltd. [1972] JJ 2009 (18 February 1972)
Deductions from interim payments under the standard RIBA contract are permissible only for liquidated and undisputed amounts; unliquidated or disputed counterclaims cannot be deducted.
- Citation
- [1972] JJ 2009
- Parties
- Claimant: Jersey Steel Co.; Defendant: Holdyne Ltd.
- Jurisdiction
- Jersey
- Judgment Date
- 18 February 1972
- Procedural Posture
- Civil / Judgment
- Outcome
- claim allowed
- Legal Topics
- Interim Payment, Deduction From Payment, Liquidated Claims, Counterclaims
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 1 Party arguments 2
Parties
Jersey Steel Co.
Claimant
Holdyne Ltd.
Defendant
Procedural Posture
Civil / Judgment
Legal Issues
- 1 Whether deductions from interim payments under a standard RIBA contract can be made for unliquidated or disputed counterclaims.
Ratio Decidendi
Deductions from interim payments under the standard RIBA contract are permissible only for liquidated and undisputed amounts; unliquidated or disputed counterclaims cannot be deducted.
Court Disposition
claim allowed
Orders
- Defendant may not deduct unliquidated or disputed counterclaims from interim payment due under the interim certificate.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment