L'Eau Des Iles Jersey Ltd. v A.E. Smith & Sons Ltd. [1999] JLR_Note 2b (04 March 1999)

L'Eau Des Iles Jersey Ltd. v A.E. Smith & Sons Ltd. [1999] JLR_Note 2b (04 March 1999)

An order for security for costs should not be made if it would stifle a valid claim.

Parties
Applicant: L'Eau Des Iles Jersey Ltd.; Respondent: A. E. Smith & Sons Ltd.
Jurisdiction
Jersey
Judgment Date
04 March 1999
Procedural Posture
Civil / Interlocutory
Outcome
Application for security for costs refused
Legal Topics
Security for Costs, Costs, Access to Justice

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Party arguments 2
Sign in to unlock

Parties

L'Eau Des Iles Jersey Ltd.

Applicant

A. E. Smith & Sons Ltd.

Respondent

Procedural Posture

Civil / Interlocutory

  1. 1 Whether an order for security for costs would stifle a valid claim

Ratio Decidendi

An order for security for costs should not be made if it would stifle a valid claim.

Court Disposition

Application for security for costs refused

Orders

  • No order for security for costs