[2024] KEHC 729 (KLR)

[2024] KEHC 729 (KLR)

The court held that its role in judicial review is confined to assessing the legality, rationality, and procedural propriety of the respondent's decision, not to re-evaluate the merits or evidence underlying the procurement process. The applicants' arguments regarding the expiry of the tender validity period and the...

Source-derived case information.

Citation
[2024] KEHC 729 (KLR)
Parties
Applicant: Accounting Officers, East Africa Portland Cement Plc; Applicant: East Africa Portland Cement Plc; Respondent: Public Procurement Administrative Review Board; Interested Party: Spenomatic Kenya Limited; Interested Party: Central Electricals International Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Application E140 of 2023
Procedural Posture
Judicial Review / Judgment
Outcome
application dismissed
Judges
J Ngaah
Legal Topics
Public Procurement Review, Judicial Review Standards, Tender Evaluation Process, Administrative Tribunal Powers
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Review Judicial Review Standards Tender Evaluation Process Administrative Tribunal Powers

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 15 Party arguments 2
Sign in to unlock

Parties

Accounting Officers, East Africa Portland Cement Plc

Applicant

East Africa Portland Cement Plc

Applicant

Public Procurement Administrative Review Board

Respondent

Spenomatic Kenya Limited

Interested Party

Central Electricals International Limited

Interested Party

Procedural Posture

Judicial Review / Judgment

  1. 1 Whether the respondent's decision to direct re-evaluation of the tender after expiry of the tender validity period was illegal, irrational, or unreasonable.
  2. 2 Whether the respondent acted outside its mandate by evaluating technical compliance of tenders, contrary to statutory provisions.
  3. 3 Whether the respondent's decision was inconsistent with its prior findings regarding the prorating of marks in technical evaluation.

Ratio Decidendi

The court held that its role in judicial review is confined to assessing the legality, rationality, and procedural propriety of the respondent's decision, not to re-evaluate the merits or evidence underlying the procurement process. The applicants' arguments regarding the expiry of the tender validity period and the alleged inconsistency in the respondent's approach to prorating marks were either not raised at the appropriate stage or not substantiated. The court found no evidence that the respondent required prorating of marks contrary to its earlier decision. Furthermore, any challenge to the respondent's prior decision should have been made within the statutory review period, failing...

Court Disposition

application dismissed

Orders

  • The applicants' motion dated 18 December 2023 is dismissed.
  • Each party shall bear its own costs.