The court found that the application for stay of execution was made without unreasonable delay, as it was filed about one month after the impugned judgment. The applicant demonstrated that it would suffer substantial loss if forced to pay the increased rent before the appeal is determined, as the increment was...

Source-derived case information.

Citation
[2020] KEELC 1651 (KLR)
Parties
Appellant: African Arts Limited; Respondent: Shazmeer Enterprises Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 51 of 2019
Procedural Posture
Civil Appeal / Ruling on Stay of Execution Pending Appeal
Outcome
Application for stay of execution allowed on condition.
Legal Topics
Rent Increase Disputes, Stay of Execution, Landlord Tenant Relations, Security for Performance
Source Language
en
Land and Property Civil Procedure Rent Increase Disputes Stay of Execution Landlord Tenant Relations Security for Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

African Arts Limited

Appellant

Shazmeer Enterprises Limited

Respondent

Procedural Posture

Civil Appeal / Ruling on Stay of Execution Pending Appeal

  1. 1 Whether the applicant is entitled to a stay of execution of the judgment and orders of the Business Premises Rent Tribunal pending appeal.
  2. 2 Whether the application for stay was made without unreasonable delay.
  3. 3 Whether the applicant will suffer substantial loss if stay is not granted.

Ratio Decidendi

The court found that the application for stay of execution was made without unreasonable delay, as it was filed about one month after the impugned judgment. The applicant demonstrated that it would suffer substantial loss if forced to pay the increased rent before the appeal is determined, as the increment was significant and could halt its business operations. However, the court noted that the respondent's ability to refund any sums paid was not challenged, and any overpayment could be converted into future rent. Balancing the interests of both parties, the court exercised its discretion to grant a conditional stay of execution, requiring the applicant to pay half of the assessed rent as...

Court Disposition

Application for stay of execution allowed on condition.

Orders

  • Stay of execution granted on condition that the applicant pays half of the assessed rent (Kshs.74,943 exclusive of VAT) to the respondent with effect from 1st February 2019.
  • Applicant to pay all arrears of rent at the rate of Kshs.74,943 per month within three months from the date of ruling; in default, respondent may levy distress.