[2019] KEHC 1940 (KLR)
The court found that the plaintiff had established its claim for the certified sums under the construction contract, as the defendant failed to pay the amounts certified by the architect and did not contest the claim. The court further held that the plaintiff was entitled to special damages for costs incurred in maintaining the site after suspension, as these were specifically pleaded, proved by receipts, and supported by an architect's certificate. The court reiterated that general damages are not awardable for breach of contract. Interest was awarded at the contractual rate of 18% per annum on the certified sum from the date of default, and at 12% per annum on the special damages from...
- Citation
- [2019] KEHC 1940 (KLR)
- Parties
- Plaintiff: Aggregate Construction Limited; Defendant: Ashleah Developers Limited
- Court
- High Court
- Court Station
- High Court at Nairobi (Milimani Commercial Courts)
- Jurisdiction
- Kenya
- Judgment Date
- 20 November 2019
- Case Number
- Civil Case 434 of 2016
- Procedural Posture
- Civil Case / Final Judgment
- Outcome
- Judgment for the plaintiff for certified sums, special damages, interest, and costs.
- Judges
- DAS Majanja
- Legal Topics
- Breach of Contract, Construction Contracts, Special Damages, Summary Judgment
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Aggregate Construction Limited
Plaintiff
Ashleah Developers Limited
Defendant
Procedural Posture
Civil Case / Final Judgment
Legal Issues
- 1 Whether the defendant breached the construction contract by failing to pay certified sums for work done.
- 2 Whether the plaintiff is entitled to special damages for costs incurred in maintaining the site after suspension of the contract.
- 3 Whether general damages are awardable for breach of contract in this context.
Ratio Decidendi
The court found that the plaintiff had established its claim for the certified sums under the construction contract, as the defendant failed to pay the amounts certified by the architect and did not contest the claim. The court further held that the plaintiff was entitled to special damages for costs incurred in maintaining the site after suspension, as these were specifically pleaded, proved by receipts, and supported by an architect's certificate. The court reiterated that general damages are not awardable for breach of contract. Interest was awarded at the contractual rate of 18% per annum on the certified sum from the date of default, and at 12% per annum on the special damages from...
Court Disposition
Judgment for the plaintiff for certified sums, special damages, interest, and costs.
Orders
- The defendant shall pay the plaintiff Kshs. 62,413,634.60 with interest at 18% per annum from 2nd July 2014 until payment in full.
- The defendant shall pay the plaintiff Kshs. 21,377,568.46 with interest at 12% per annum from the date of filing suit until payment in full.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment