[2025] KEHC 5728 (KLR)

[2025] KEHC 5728 (KLR)

The High Court found that the respondent did not fully perform its contractual obligations, as evidenced by correspondence and the lack of completion reports or test pumping results. The trial magistrate erred by awarding the full contract sum without adequate analysis of the evidence. The court held that, although...

Source-derived case information.

Citation
[2025] KEHC 5728 (KLR)
Parties
Appellant: The Agricultural Society of Kenya; Respondent: Artesian Kenya Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Appeal 705 of 2019
Procedural Posture
Civil Appeal / Judgment
Outcome
Appeal allowed in part; trial court's award set aside and substituted with a reduced sum; appellant awarded costs of the appeal.
Judges
REA Ougo
Legal Topics
Breach of Contract, Contractual Entitlements, Quantum of Damages, Mitigation of Loss
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Contractual Entitlements Quantum of Damages Mitigation of Loss

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

The Agricultural Society of Kenya

Appellant

Artesian Kenya Limited

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the respondent was entitled to the full contract sum for drilling and equipping the borehole despite alleged incomplete performance.
  2. 2 Whether the appellant was justified in withholding payment and claiming damages for breach of contract and misrepresentation.
  3. 3 Whether time was of the essence in the contract and the effect of non-compliance with the stipulated completion period.

Ratio Decidendi

The High Court found that the respondent did not fully perform its contractual obligations, as evidenced by correspondence and the lack of completion reports or test pumping results. The trial magistrate erred by awarding the full contract sum without adequate analysis of the evidence. The court held that, although the respondent mobilized and drilled to a depth of 131 metres, there was no proof of completion of all contractual stages. The appellant's claim that time was of the essence was unsupported by express contractual terms, and the respondent was entitled to payment for work actually done, not the full contract amount. The respondent was not entitled to demobilization costs or...

Court Disposition

Appeal allowed in part; trial court's award set aside and substituted with a reduced sum; appellant awarded costs of the appeal.

Orders

  • The judgment of the trial court awarding the respondent Kshs 5,081,680/- is set aside.
  • The respondent is awarded Kshs 265,800/- only, being mobilization and drilling costs.