[2024] KEHC 3288 (KLR)

[2024] KEHC 3288 (KLR)

The appellant bore the burden of proving, on a balance of probabilities, that it was entitled to the outstanding payment for the construction project. While it demonstrated that it was awarded the tender, entered into a contract, and received partial payments, it failed to produce completion or acceptance...

Source-derived case information.

Citation
[2024] KEHC 3288 (KLR)
Parties
Appellant: Ainushamsi Construction & Transporters Company Limited; Respondent: County Government Of Vihiga
Court
High Court
Court Station
High Court at Vihiga
Jurisdiction
Kenya
Case Number
Civil Appeal E003 of 2022
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed
Judges
JN Kamau
Legal Topics
Public Procurement Disputes, Burden of Proof, Construction Contracts, Evidence Requirements
Source Language
en
Commercial and Corporate Civil Procedure Public Procurement Disputes Burden of Proof Construction Contracts Evidence Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 12 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Ainushamsi Construction & Transporters Company Limited

Appellant

County Government Of Vihiga

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the trial magistrate erred in law and fact by failing to consider the evidence tendered by the appellant in prosecuting the claim against the respondent.
  2. 2 Whether the trial magistrate erred in law and fact by relying on facts not pleaded and issues not raised by the parties in arriving at his decision.

Ratio Decidendi

The appellant bore the burden of proving, on a balance of probabilities, that it was entitled to the outstanding payment for the construction project. While it demonstrated that it was awarded the tender, entered into a contract, and received partial payments, it failed to produce completion or acceptance certificates as required by the Public Procurement and Disposal Regulations, 2006. The absence of these certificates meant the appellant did not sufficiently prove that the works were completed to the satisfaction of the respondent and thus did not establish entitlement to the claimed balance. The trial court was correct in finding that the appellant failed to discharge its burden of...

Court Disposition

appeal dismissed

Orders

  • The appellant's appeal is dismissed.
  • Each party will bear its own costs of the appeal.