[2025] KEHC 1018 (KLR)

[2025] KEHC 1018 (KLR)

The court found that the applicants had established a prima facie case for the grant of interim injunctive relief. The contracts in question contained arbitration clauses, and the applicants demonstrated that the respondents' threatened actions—such as terminating contracts, seizing sites, and interfering with...

Source-derived case information.

Citation
[2025] KEHC 1018 (KLR)
Parties
Applicant: Allweather Investments Co. Ltd; Applicant: Columbia Developers Limited; Applicant: Samaha Company Limited; Appellant: Glenn Steam Engineering Works Limited; Applicant: Lantana Africa Limited; Applicant: Globetrek Systems K) Limited; Applicant: Kinde Engineering Works Limited; Applicant: Pinnie Ageny Limited; Respondent: The Attorney General of the Republic of Kenya; Respondent: The Cabinet Secretary, Ministry for Education; Respondent: The Principal Secretary, State Department of Early Learning and Basic Education
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Application E055 of 2025
Procedural Posture
Miscellaneous Application / Ruling on Interim Injunction Pending Arbitration
Outcome
Application allowed; interim injunctive relief granted as prayed pending arbitration.
Judges
JWW Mong'are
Legal Topics
Interim Measures, Arbitration Clauses, Injunctive Relief, Contractual Disputes, Preservation of Subject Matter, Service of Process
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Interim Measures Arbitration Clauses Injunctive Relief Contractual Disputes Preservation of Subject Matter +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Allweather Investments Co. Ltd

Applicant

Columbia Developers Limited

Applicant

Samaha Company Limited

Applicant

Glenn Steam Engineering Works Limited

Appellant

Lantana Africa Limited

Applicant

Globetrek Systems K) Limited

Applicant

Kinde Engineering Works Limited

Applicant

Pinnie Ageny Limited

Applicant

The Attorney General of the Republic of Kenya

Respondent

The Cabinet Secretary, Ministry for Education

Respondent

The Principal Secretary, State Department of Early Learning and Basic Education

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Interim Injunction Pending Arbitration

  1. 1 Whether the High Court should grant interim injunctive relief to restrain the respondents from interfering with the applicants' contractual rights pending arbitration.
  2. 2 Whether the applicants have established a prima facie case for the preservation of the subject matter of the contracts pending arbitration.
  3. 3 Whether the respondents were properly served and had notice of the application.

Ratio Decidendi

The court found that the applicants had established a prima facie case for the grant of interim injunctive relief. The contracts in question contained arbitration clauses, and the applicants demonstrated that the respondents' threatened actions—such as terminating contracts, seizing sites, and interfering with retention sums—would irreparably prejudice their contractual rights and the subject matter of the dispute. The court was satisfied that the respondents had been properly served but failed to respond. Relying on section 7 of the Arbitration Act and relevant case law, the court held that it had jurisdiction to grant interim measures to preserve the status quo and protect the...

Court Disposition

Application allowed; interim injunctive relief granted as prayed pending arbitration.

Orders

  • An order restraining the 2nd and 3rd respondents from taking any further adverse action in respect to the contract pending arbitration.
  • An order of injunction restraining the 2nd and 3rd respondents from seizing or taking over construction sites, equipment, plant, machinery, materials, or interfering with the applicants' possession of construction sites and materials pending arbitration.