The court found that valid contracts existed between the plaintiffs and the defendant, evidenced by executed agreements and certificates of completion or partial completion. The defendant's failure to pay for certified works constituted a breach of contract. Investigations by the Ethics and Anti-Corruption...

Source-derived case information.

Citation
[2022] KEHC 10859 (KLR)
Parties
Plaintiff: Aridsun Contractors; Plaintiff: Katungate Contractors Ltd; Plaintiff: Syano Roads & Bridges Co. Ltd; Plaintiff: Konza Works Construction & Engineering; Defendant: County Government of Kitui
Court
High Court
Court Station
High Court at Kitui
Jurisdiction
Kenya
Case Number
Civil Suit 1 of 2019
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiffs.
Judges
RK Limo
Legal Topics
Breach of Contract, Public Procurement, Specific Performance, Damages for Breach, Contract Enforcement
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Public Procurement Specific Performance Damages for Breach Contract Enforcement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 10 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Aridsun Contractors

Plaintiff

Katungate Contractors Ltd

Plaintiff

Syano Roads & Bridges Co. Ltd

Plaintiff

Konza Works Construction & Engineering

Plaintiff

County Government of Kitui

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether valid contracts existed between the plaintiffs and the defendant for public works in Kitui County.
  2. 2 Whether the defendant breached the terms of the contracts by failing to pay for certified works.
  3. 3 Whether the plaintiffs are entitled to specific performance and/or payment of certified sums.

Ratio Decidendi

The court found that valid contracts existed between the plaintiffs and the defendant, evidenced by executed agreements and certificates of completion or partial completion. The defendant's failure to pay for certified works constituted a breach of contract. Investigations by the Ethics and Anti-Corruption Commission did not invalidate the contracts, and the defendant's reliance on internal processes or budgetary constraints did not justify non-payment. The plaintiffs were entitled to payment for the certified sums as per the contracts, but not to general damages, as such are not ordinarily recoverable for breach of contract. Interest and costs were awarded to compensate for the delay and...

Court Disposition

Judgment for the plaintiffs.

Orders

  • Defendant to pay Aridsun Contractors Ltd KES 22,610,133.33.
  • Defendant to pay Katungate Contractors Ltd KES 27,698,510.16.