[2023] KEHC 17641 (KLR)

[2023] KEHC 17641 (KLR)

The court found that a contract was executed between the Plaintiff and the Defendants, evidenced by signed documents and subsequent conduct, including reconnaissance and submission of an Inception Report. However, the procurement process was fundamentally flawed, as the contract was signed before the expiry of the...

Source-derived case information.

Citation
[2023] KEHC 17641 (KLR)
Parties
Plaintiff: Associates in Integrated Development (Africa) Limited; Defendant: County Government of Bomet; Defendant: The County Secretary County Government of Bomet; Defendant: The Chief Officer Economic Planning County Government of Bomet
Court
High Court
Court Station
High Court at Bomet
Jurisdiction
Kenya
Case Number
Civil Case 1 of 2019
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiff awarded Kshs 5,000,000 as compensation for work done; costs and interest at court rates granted; other prayers declined.
Judges
RL Korir
Legal Topics
Public Procurement, Breach of Contract, Contractual Damages, Tender Process Irregularities, Evidence Admissibility, Remedies for Illegal Contracts
Source Language
en
Commercial and Corporate Civil Procedure Public Procurement Breach of Contract Contractual Damages Tender Process Irregularities Evidence Admissibility Remedies for Illegal Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 13 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Associates in Integrated Development (Africa) Limited

Plaintiff

County Government of Bomet

Defendant

The County Secretary County Government of Bomet

Defendant

The Chief Officer Economic Planning County Government of Bomet

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether there was a valid and enforceable contract between the Plaintiff and the Defendants.
  2. 2 Whether the Defendants breached the terms of the contract.
  3. 3 Whether the procurement process was lawful and compliant with the Public Procurement and Asset Disposal Act.

Ratio Decidendi

The court found that a contract was executed between the Plaintiff and the Defendants, evidenced by signed documents and subsequent conduct, including reconnaissance and submission of an Inception Report. However, the procurement process was fundamentally flawed, as the contract was signed before the expiry of the statutory 14-day period following notification, and there was no evidence that all bidders were properly notified as required by the Public Procurement and Asset Disposal Act. The court held that the contract, though valid as between the parties, was unenforceable due to statutory non-compliance. Nevertheless, the Plaintiff was an innocent party and not complicit in the...

Court Disposition

Plaintiff awarded Kshs 5,000,000 as compensation for work done; costs and interest at court rates granted; other prayers declined.

Orders

  • Judgment entered for the Plaintiff against the Defendants in the sum of Kshs 5,000,000.
  • Plaintiff awarded costs of the suit.