[2018] KEHC 1211 (KLR)

[2018] KEHC 1211 (KLR)

The court found that the contract between the parties, though evidenced by a series of documents and not a single written agreement, was clear in its requirement that works be measured jointly and certified by the project manager. The project manager's certificate, issued after joint measurement, established the sum...

Source-derived case information.

Citation
[2018] KEHC 1211 (KLR)
Parties
Plaintiff: Aswa Developers & Contractors Limited; Defendant: Compact Freight Systems Limited
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 85 of 2009
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff in the sum of Kshs.6,803,985.30 plus interest and costs; claim for value of materials dismissed.
Judges
CA Otieno, DO Chepkwony
Legal Topics
Construction Contracts, Contractual Certificates, Breach of Contract, Fraud and Misrepresentation, Quantum of Damages
Source Language
english
Commercial and Corporate Civil Procedure Construction Contracts Contractual Certificates Breach of Contract Fraud and Misrepresentation Quantum of Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Aswa Developers & Contractors Limited

Plaintiff

Compact Freight Systems Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the plaintiff is entitled to the sum claimed on the basis of the valuation certificate issued by the project manager after joint measurement exercises.
  2. 2 Whether the defendant proved allegations of fraud and misrepresentation sufficient to defeat the plaintiff's claim.
  3. 3 Whether the plaintiff proved entitlement to the value of materials allegedly detained by the defendant.

Ratio Decidendi

The court found that the contract between the parties, though evidenced by a series of documents and not a single written agreement, was clear in its requirement that works be measured jointly and certified by the project manager. The project manager's certificate, issued after joint measurement, established the sum due to the plaintiff. The defendant's allegations of fraud and misrepresentation were not proved to the requisite standard, and no evidence was adduced to show that the project manager's professional opinion was tainted. The court held that the certificate bound both parties, and the defendant's own witness admitted the sum was owing. The claim for the value of materials left...

Court Disposition

Judgment for the plaintiff in the sum of Kshs.6,803,985.30 plus interest and costs; claim for value of materials dismissed.

Orders

  • Judgment entered for the plaintiff against the defendant in the sum of Kshs.6,803,985.30.
  • Interest awarded at prevailing court rates from 14/10/2008 until payment in full.