[2021] KEHC 53 (KLR)

[2021] KEHC 53 (KLR)

The court found that the guarantee issued by the bank was a separate and independent contract from the main contract between the applicant and the 1st respondent. The applicant, not being a party to the guarantee, could not restrain the bank from fulfilling its obligations to the 1st respondent upon demand. The...

Source-derived case information.

Citation
[2021] KEHC 53 (KLR)
Parties
Applicant: Attain Enterprise Solution Limited; Respondent: Sacco Societies Regulatory Authority; Respondent: Development Bank of Kenya Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Civil Application E485 of 2021
Procedural Posture
Miscellaneous Application / Ruling on Application for Interim Measure of Protection Under Section 7 of the Arbitration Act, 1995
Outcome
application dismissed with costs to the respondents; interim orders discharged
Judges
DAS Majanja
Legal Topics
Interim Measures of Protection, Performance Bonds, Arbitration Agreements, Mandatory Injunctions
Source Language
en
Commercial and Corporate Civil Procedure Interim Measures of Protection Performance Bonds Arbitration Agreements Mandatory Injunctions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Attain Enterprise Solution Limited

Applicant

Sacco Societies Regulatory Authority

Respondent

Development Bank of Kenya Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application for Interim Measure of Protection Under Section 7 of the Arbitration Act, 1995

  1. 1 Whether the applicant is entitled to an interim measure of protection under section 7 of the Arbitration Act, 1995.
  2. 2 Whether the court can restrain the enforcement of a performance guarantee pending arbitration.
  3. 3 Whether the 1st respondent should be compelled to deposit the contract sums with the applicant's advocates pending arbitration.

Ratio Decidendi

The court found that the guarantee issued by the bank was a separate and independent contract from the main contract between the applicant and the 1st respondent. The applicant, not being a party to the guarantee, could not restrain the bank from fulfilling its obligations to the 1st respondent upon demand. The court emphasized that the subject matter of the arbitration was the contract performance dispute, not the guarantee itself, and that the arbitral tribunal would not adjudicate on the guarantee. Granting the interim measure sought would improperly encroach on the arbitral tribunal's jurisdiction and undermine the independence of the guarantee. The court also held that compelling the...

Court Disposition

application dismissed with costs to the respondents; interim orders discharged

Orders

  • The Notice of Motion dated 25th June 2021 is dismissed with costs to the respondents.
  • The interim orders in force are hereby discharged forthwith.