[2023] KEHC 24756 (KLR)

[2023] KEHC 24756 (KLR)

The court found that the plaintiff had proved its case on a balance of probabilities. The evidence, including payment certificates and correspondence from the defendants, established that the sum of Kshs. 256,845,079 was due and owing for construction works performed. The court determined that the defendants, as...

Source-derived case information.

Citation
[2023] KEHC 24756 (KLR)
Parties
Plaintiff: Bajrang Construction Limited; Defendant: Barham Dev Vasisht; Defendant: Sangeeta Barham Vasisht; Interested Party: Administrators, Thika School of Medical and Health Sciences Limited
Court
High Court
Court Station
High Court at Kiambu
Jurisdiction
Kenya
Case Number
Civil Case E005 of 2022
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff against the defendants jointly and severally.
Judges
PM Mulwa
Legal Topics
Lifting Corporate Veil, Director Liability, Breach of Contract, Fraudulent Conduct, Company Law, Contract Enforcement
Source Language
en
Commercial and Corporate Civil Procedure Lifting Corporate Veil Director Liability Breach of Contract Fraudulent Conduct Company Law Contract Enforcement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Bajrang Construction Limited

Plaintiff

Barham Dev Vasisht

Defendant

Sangeeta Barham Vasisht

Defendant

Administrators, Thika School of Medical and Health Sciences Limited

Interested Party

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff proved its case against the defendants on a balance of probabilities.
  2. 2 Whether the court should pierce the corporate veil of Thika School of Medical and Health Sciences Limited.

Ratio Decidendi

The court found that the plaintiff had proved its case on a balance of probabilities. The evidence, including payment certificates and correspondence from the defendants, established that the sum of Kshs. 256,845,079 was due and owing for construction works performed. The court determined that the defendants, as directors, used the company as a vehicle for fraud and personal benefit, misrepresenting their intentions to pay and diverting company resources. The defendants' failure to controvert the plaintiff's evidence, coupled with their admissions and conduct, justified piercing the corporate veil. The court held the defendants personally liable for the debt, with interest at commercial...

Court Disposition

Judgment for the plaintiff against the defendants jointly and severally.

Orders

  • Judgment entered in favour of the plaintiff against the defendants jointly and severally for Kshs. 256,845,079.
  • The sum shall attract interest at commercial rates from the date of filing suit until payment in full.