[1986] KECA 72 (KLR)

[1986] KECA 72 (KLR)

The Court of Appeal held that there was no concluded contract between the parties because the date for possession of the site, a critical term, was expressly left to be agreed upon later and was never settled. The correspondence and tender documents showed that the parties intended to negotiate and agree on this...

Source-derived case information.

Citation
[1986] KECA 72 (KLR)
Parties
Appellant: Bakshish Singh & Brothers; Respondent: Panafric Hotels Limited
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 5 of 1984
Procedural Posture
Civil Appeal / Appeal From High Court Judgment
Outcome
Appeal allowed; High Court judgment set aside; suit dismissed with costs to contractor; cross-appeal dismissed with costs.
Judges
JM Gachuhi
Legal Topics
Building Contracts, Offer and Acceptance, Conditions Precedent, Damages for Breach, Mitigation of Loss
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Offer and Acceptance Conditions Precedent Damages for Breach Mitigation of Loss

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Bakshish Singh & Brothers

Appellant

Panafric Hotels Limited

Respondent

Procedural Posture

Civil Appeal / Appeal From High Court Judgment

  1. 1 Whether the tender and letter of acceptance constituted a concluded contract between the parties.
  2. 2 Whether the absence of an agreed date for possession of the site rendered the contract incomplete.
  3. 3 Whether damages were payable for breach and, if so, how they should be assessed.

Ratio Decidendi

The Court of Appeal held that there was no concluded contract between the parties because the date for possession of the site, a critical term, was expressly left to be agreed upon later and was never settled. The correspondence and tender documents showed that the parties intended to negotiate and agree on this essential point after the purported acceptance. Without agreement on this term, there was no binding contract. Consequently, there could be no breach and no damages were payable. The High Court's judgment awarding damages to the employer was set aside, and the contractor's appeal was allowed. The employer's cross-appeal on damages was dismissed.

Court Disposition

Appeal allowed; High Court judgment set aside; suit dismissed with costs to contractor; cross-appeal dismissed with costs.

Orders

  • The appeal is allowed with costs to the contractor.
  • The judgment of the High Court is set aside.