[2012] KEHC 4187 (KLR)

[2012] KEHC 4187 (KLR)

The court found that although the Defendant eventually honoured the guarantee, it did so after the Plaintiff had already initiated proceedings to enforce payment. The Defendant failed to promptly communicate the settlement to the Plaintiff and did not take timely steps to resolve the matter or inform the Plaintiff...

Source-derived case information.

Citation
[2012] KEHC 4187 (KLR)
Parties
Plaintiff: Bamburi Cement Limited; Defendant: Bank of Africa Kenya Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 78 of 2010
Procedural Posture
Civil Suit / Ruling on Costs After Settlement of Principal Claim
Outcome
Costs of the suit and the application dated 23rd April 2010 awarded to the Plaintiff.
Judges
C.N Mutava
Legal Topics
Bank Guarantees, Enforcement of Guarantees, Costs Follow Event, Summary Judgment Applications
Source Language
en
Commercial and Corporate Civil Procedure Bank Guarantees Enforcement of Guarantees Costs Follow Event Summary Judgment Applications

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Bamburi Cement Limited

Plaintiff

Bank of Africa Kenya Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Costs After Settlement of Principal Claim

  1. 1 Whether the Plaintiff is entitled to costs of the suit after the Defendant settled the principal claim.
  2. 2 Whether the Plaintiff is entitled to costs of the application for summary judgment filed after the principal sum was paid.

Ratio Decidendi

The court found that although the Defendant eventually honoured the guarantee, it did so after the Plaintiff had already initiated proceedings to enforce payment. The Defendant failed to promptly communicate the settlement to the Plaintiff and did not take timely steps to resolve the matter or inform the Plaintiff of the court orders that delayed payment. Both parties contributed to the delay in finalising the suit, but the Plaintiff was justified in pursuing enforcement and the related application. As costs follow the event, and the Defendant's conduct contributed to the continuation of proceedings, the Plaintiff is entitled to the costs of the suit and the application for summary judgment.

Court Disposition

Costs of the suit and the application dated 23rd April 2010 awarded to the Plaintiff.

Orders

  • The Defendant shall pay the Plaintiff the costs of the suit.
  • The Defendant shall pay the Plaintiff the costs of the application dated 23rd April 2010.