[2008] KEHC 3020 (KLR)

[2008] KEHC 3020 (KLR)

The court found that the applicant had demonstrated the likelihood of suffering substantial loss if stay was not granted, given the respondent's unemployment and inability to refund the decretal sum if the appeal succeeded. The court held that the 30-day delay in filing the application was not inordinate. However,...

Source-derived case information.

Citation
[2008] KEHC 3020 (KLR)
Parties
Appellant: Bamburi Cement Ltd; Respondent: Joseph Kamuli Kaindi
Court
High Court
Court Station
High Court at Machakos
Jurisdiction
Kenya
Case Number
Civil Appeal 193 of 2007
Procedural Posture
Civil Appeal / Ruling on Stay of Execution Pending Appeal
Outcome
Application for stay of execution pending appeal granted, subject to conditions.
Legal Topics
Stay of Execution, Wrongful Dismissal, Substantial Loss, Security for Due Performance
Source Language
en
Civil Procedure Employment and Labour Stay of Execution Wrongful Dismissal Substantial Loss Security for Due Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Bamburi Cement Ltd

Appellant

Joseph Kamuli Kaindi

Respondent

Procedural Posture

Civil Appeal / Ruling on Stay of Execution Pending Appeal

  1. 1 Whether the applicant has satisfied the conditions for grant of stay of execution pending appeal under Order XLI Rule 4 of the Civil Procedure Rules.
  2. 2 Whether the applicant will suffer substantial loss if stay is not granted.
  3. 3 Whether the application was made without unreasonable delay.

Ratio Decidendi

The court found that the applicant had demonstrated the likelihood of suffering substantial loss if stay was not granted, given the respondent's unemployment and inability to refund the decretal sum if the appeal succeeded. The court held that the 30-day delay in filing the application was not inordinate. However, to balance the interests of both parties, the court ordered that the entire decretal amount be deposited in a joint interest-earning account in the names of both parties' advocates within 21 days as security for due performance. Failure to comply would result in the lapse of the stay order and execution could proceed. Costs of the application were ordered to abide the outcome of...

Court Disposition

Application for stay of execution pending appeal granted, subject to conditions.

Orders

  • Stay of execution pending appeal granted.
  • Applicant to deposit the entire decretal amount in a joint interest-earning account in the names of both parties' advocates within 21 days.