[2019] KEHC 12431 (KLR)

[2019] KEHC 12431 (KLR)

The court found that the plaintiff had proved its claim on a balance of probabilities, as the advances to the 1st defendant were supported by documentary evidence, and the guarantees and securities executed by the 2nd and 3rd defendants were valid. The defendants' defence was unsupported by evidence, as they failed...

Source-derived case information.

Citation
[2019] KEHC 12431 (KLR)
Parties
Plaintiff: Bank of India; Defendant: Raman Enterprises Limited; Defendant: Mansukh Baldeo Das; Defendant: Purnima Das
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 214 of 2013
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff
Judges
DAS Majanja
Legal Topics
Loan Facilities, Guarantees and Indemnities, Secured Transactions, Interest Rates, Debt Recovery
Source Language
en
Banking and Finance Commercial and Corporate Loan Facilities Guarantees and Indemnities Secured Transactions Interest Rates Debt Recovery

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Bank of India

Plaintiff

Raman Enterprises Limited

Defendant

Mansukh Baldeo Das

Defendant

Purnima Das

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendants are indebted to the plaintiff for the amount claimed under the loan facilities advanced.
  2. 2 Whether the interest rate claimed by the plaintiff is justified and supported by evidence.
  3. 3 Whether the securities provided by the defendants were properly enforced and whether the plaintiff is entitled to judgment for the outstanding sum.

Ratio Decidendi

The court found that the plaintiff had proved its claim on a balance of probabilities, as the advances to the 1st defendant were supported by documentary evidence, and the guarantees and securities executed by the 2nd and 3rd defendants were valid. The defendants' defence was unsupported by evidence, as they failed to attend the hearing. The court held that the plaintiff was entitled to judgment for the outstanding sum. However, the plaintiff failed to prove the applicable base rate for the claimed interest of 28.5% per annum, so the court awarded interest at 13% per annum from 1st December 2012. The defendants were held jointly and severally liable for the debt, and the plaintiff was...

Court Disposition

judgment for the plaintiff

Orders

  • Judgment entered for the plaintiff against the defendants jointly and severally for Kshs. 58,729,451.65 with interest at 13% per annum from 1st December 2012.
  • The defendants shall bear the costs of the suit.