[2018] KEHC 3232 (KLR)

[2018] KEHC 3232 (KLR)

The court found that while the appellant's water supply was indeed disconnected by the respondents, his pleadings were inconsistent with his evidence regarding the dates of disconnection. The appellant was given notice prior to disconnection, and the action was justified due to his breach of the water project's...

Source-derived case information.

Citation
[2018] KEHC 3232 (KLR)
Parties
Appellant: Benjamin Mwongera; Respondent: Benjamin Mutuma (Chairman); Respondent: Joshua Mururu (Secretary)
Court
High Court
Court Station
High Court at Meru
Jurisdiction
Kenya
Case Number
Civil Appeal 90 of 2010
Procedural Posture
Civil Appeal / Judgment
Outcome
Appeal dismissed with directions for possible reconnection upon undertaking to abide by project rules. Each party to bear own costs.
Legal Topics
Injunctions, Pleadings and Particulars, Water Rights, Membership of Societies
Source Language
en
Civil Procedure Land and Property Injunctions Pleadings and Particulars Water Rights Membership of Societies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Benjamin Mwongera

Appellant

Benjamin Mutuma (Chairman)

Respondent

Joshua Mururu (Secretary)

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the trial court erred in dismissing the appellant's suit for uncertainty regarding the dates of water disconnection.
  2. 2 Whether the suit was filed out of time despite leave having been granted.
  3. 3 Whether the appellant was a member of the water project and subject to its rules and regulations.

Ratio Decidendi

The court found that while the appellant's water supply was indeed disconnected by the respondents, his pleadings were inconsistent with his evidence regarding the dates of disconnection. The appellant was given notice prior to disconnection, and the action was justified due to his breach of the water project's rules and regulations, of which he was a member. The trial court's reliance on procedural technicalities was noted, but the appellate court determined that the appellant's failure to comply with the project's rules and the lack of clear evidence on damages precluded granting the reliefs sought. However, the court directed that the appellant could be reconnected to the water supply...

Court Disposition

Appeal dismissed with directions for possible reconnection upon undertaking to abide by project rules. Each party to bear own costs.

Orders

  • The appeal is dismissed.
  • The committee of the Respondent water Project is directed to reconnect the appellant to the water supply if the project still exists, subject to the appellant undertaking to abide by the project's rules and regulations.