[2023] KEELC 21860 (KLR)

[2023] KEELC 21860 (KLR)

The court found that the Plaintiff's building was wholly within the visibility diamond, an area where construction is expressly prohibited for public safety under the Engineering Manual. The Plaintiff was notified and warned to stop construction but disregarded the warnings and continued building. The Defendant's...

Source-derived case information.

Citation
[2023] KEELC 21860 (KLR)
Parties
Plaintiff: Joseph Kipkorir Biwott; Defendant: Kenya Railways Corporation
Court
Environment and Land Court
Court Station
Environment and Land Court at Eldoret
Jurisdiction
Kenya
Case Number
Environment & Land Case E004 of 2021
Procedural Posture
Environment and Land Case / Judgment
Outcome
Plaintiff's case dismissed with no order as to costs.
Judges
EO Obaga
Legal Topics
Trespass to Land, Demolition of Structures, Injunctive Relief, Public Safety Regulation
Source Language
en
Land and Property Civil Procedure Trespass to Land Demolition of Structures Injunctive Relief Public Safety Regulation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Joseph Kipkorir Biwott

Plaintiff

Kenya Railways Corporation

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the Plaintiff's building was on land within the visibility diamond and if so whether the Plaintiff complied with the law regarding properties within the visibility diamond.
  2. 2 Whether the Plaintiff was notified to remove and or stop construction within the visibility diamond.
  3. 3 Whether the Defendant fully complied with the requirements of the law before carrying out the demolition.

Ratio Decidendi

The court found that the Plaintiff's building was wholly within the visibility diamond, an area where construction is expressly prohibited for public safety under the Engineering Manual. The Plaintiff was notified and warned to stop construction but disregarded the warnings and continued building. The Defendant's actions in demolishing the structure were lawful and in compliance with the relevant regulations and statutory obligations. The Plaintiff failed to prove any entitlement to damages, as the structure was illegal and lacked necessary approvals. The court further held that the Plaintiff's rights were not violated, as he was given notice and an opportunity to be heard. The...

Court Disposition

Plaintiff's case dismissed with no order as to costs.

Orders

  • The Plaintiff's suit is dismissed.
  • There is no order as to costs.