[2017] KEHC 9327 (KLR)

[2017] KEHC 9327 (KLR)

The court found that the plaintiff had not demonstrated entitlement to summary judgment because the contract was for a 24-month period, but the project was suspended after only four months. The defendant's defence that payment was tied to performance and that the plaintiff had not completed its obligations raised...

Source-derived case information.

Citation
[2017] KEHC 9327 (KLR)
Parties
Plaintiff: Bon-Arch Associates Limited; Defendant: Ninety Four Eastchurch Properties Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 173 of 2016
Procedural Posture
Civil Suit / Ruling on Application for Summary Judgment and Interlocutory Injunction
Outcome
Applications for summary judgment and interlocutory injunction dismissed with costs to the defendant.
Legal Topics
Summary Judgment, Breach of Contract, Architectural Services Contracts, Interlocutory Injunctions, Liquidated Claims
Source Language
en
Commercial and Corporate Civil Procedure Summary Judgment Breach of Contract Architectural Services Contracts Interlocutory Injunctions Liquidated Claims

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 5 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Bon-Arch Associates Limited

Plaintiff

Ninety Four Eastchurch Properties Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Application for Summary Judgment and Interlocutory Injunction

  1. 1 Whether the plaintiff is entitled to summary judgment for the claimed contractual sum.
  2. 2 Whether the plaintiff is entitled to an interlocutory injunction restraining the defendant from dealing with the suit property.
  3. 3 Whether the defendant has raised triable issues in its defence to warrant a full trial.

Ratio Decidendi

The court found that the plaintiff had not demonstrated entitlement to summary judgment because the contract was for a 24-month period, but the project was suspended after only four months. The defendant's defence that payment was tied to performance and that the plaintiff had not completed its obligations raised triable issues requiring a full trial. The court also found that the plaintiff failed to provide sufficient evidence that the suit property was in danger of being wasted, damaged, or alienated, or that the defendant intended to dispose of it to obstruct execution of a decree. The plaintiff did not establish a prima facie case with a probability of success to warrant an...

Court Disposition

Applications for summary judgment and interlocutory injunction dismissed with costs to the defendant.

Orders

  • The application for summary judgment is dismissed with costs to the defendant.
  • The application for interlocutory injunction is dismissed with costs to the defendant.