[2022] KEHC 10673 (KLR)

[2022] KEHC 10673 (KLR)

The court found that the plaintiff failed to establish a prima facie case for the grant of a temporary injunction. The contractual relationship between the parties was governed by the transport agreement, which placed the duty of care and liability for loss during transit squarely on the plaintiff. The plaintiff did...

Source-derived case information.

Citation
[2022] KEHC 10673 (KLR)
Parties
Applicant: Brits Freighters Ltd; Defendant: National Oil Corporation of Kenya
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 123 of 2019
Procedural Posture
Civil Suit / Ruling on Interlocutory Injunction Application
Outcome
application dismissed with costs to the defendant
Judges
DO Chepkwony
Legal Topics
Contract Termination, Injunctive Relief, Breach of Contract, Freedom of Contract
Source Language
en
Commercial and Corporate Civil Procedure Contract Termination Injunctive Relief Breach of Contract Freedom of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Brits Freighters Ltd

Applicant

National Oil Corporation of Kenya

Defendant

Procedural Posture

Civil Suit / Ruling on Interlocutory Injunction Application

  1. 1 Whether the plaintiff has established a prima facie case to warrant the grant of a temporary injunction restraining the defendant from taking adverse action based on the transport agreement.
  2. 2 Whether the termination of the transport agreement by the defendant was justified under the terms of the contract.
  3. 3 Whether the plaintiff will suffer irreparable harm not compensable by damages if the injunction is not granted.

Ratio Decidendi

The court found that the plaintiff failed to establish a prima facie case for the grant of a temporary injunction. The contractual relationship between the parties was governed by the transport agreement, which placed the duty of care and liability for loss during transit squarely on the plaintiff. The plaintiff did not deny collecting the consignment in question and admitted to suspending drivers involved in the alleged malpractice, but failed to prove that delivery was made as required. The agreement expressly allowed the defendant to terminate the contract in the event of fraud or material breach. The court held that the plaintiff could not seek protection from the court for its own...

Court Disposition

application dismissed with costs to the defendant

Orders

  • The plaintiff's notice of motion application dated June 13, 2019 is dismissed with costs to the defendant.