[2019] KEELRC 62 (KLR)

[2019] KEELRC 62 (KLR)

The court found that the Claimant was employed on a fixed term seasonal contract which was terminated midstream by the Respondent, allegedly due to a typographical error in the contract's expiry date. The Respondent failed to provide evidence explaining the error or justifying early termination. The court held that...

Source-derived case information.

Citation
[2019] KEELRC 62 (KLR)
Parties
Claimant: Brownson Kiteria; Respondent: Pemba Investments Limited t/a Neptune Beach Hotel
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Mombasa
Jurisdiction
Kenya
Case Number
Cause 379 of 2015
Procedural Posture
Employment Cause / Judgment
Outcome
Judgment for the Claimant.
Judges
L Ndolo
Legal Topics
Unlawful Termination, Fixed Term Contracts, Terminal Dues, Damages for Wrongful Dismissal
Source Language
en
Employment and Labour Unlawful Termination Fixed Term Contracts Terminal Dues Damages for Wrongful Dismissal

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Brownson Kiteria

Claimant

Pemba Investments Limited t/a Neptune Beach Hotel

Respondent

Procedural Posture

Employment Cause / Judgment

  1. 1 Whether the Claimant was unlawfully terminated from employment.
  2. 2 Whether the Claimant is entitled to the remedies sought, including terminal dues and damages.

Ratio Decidendi

The court found that the Claimant was employed on a fixed term seasonal contract which was terminated midstream by the Respondent, allegedly due to a typographical error in the contract's expiry date. The Respondent failed to provide evidence explaining the error or justifying early termination. The court held that the Claimant had a legitimate expectation to serve the full contract term and that the Respondent, having drafted the contract, must bear responsibility for any errors. The appropriate remedy was damages equivalent to the salary the Claimant would have earned for the remainder of the contract. The court also found that certain terminal dues were admitted by the Respondent and...

Court Disposition

Judgment for the Claimant.

Orders

  • The Respondent shall pay the Claimant a total of Kshs. 81,240 as specified in the judgment.
  • The amount shall attract interest at court rates from the date of judgment until payment in full.