[2015] KEHC 5349 (KLR)

[2015] KEHC 5349 (KLR)

The court found that the contract between the parties was not in dispute and that both parties mutually agreed to terminate it. A valuation was conducted by the Ministry of Public Works, which both parties accepted, and the defendant partially settled the amount due. The defendant's defence amounted to a mere denial...

Source-derived case information.

Citation
[2015] KEHC 5349 (KLR)
Parties
Plaintiff: Bubble Engineering Company Ltd; Defendant: Maseno University
Court
High Court
Court Station
High Court at Kisumu
Jurisdiction
Kenya
Case Number
Civil Suit 10 of 2014
Procedural Posture
Civil Suit / Ruling on Application for Judgment on Admission
Outcome
application allowed; judgment entered for plaintiff
Legal Topics
Judgment on Admission, Contract Termination, Quantum of Damages, Mutual Agreement, Valuation of Work Done
Source Language
en
Civil Procedure Commercial and Corporate Judgment on Admission Contract Termination Quantum of Damages Mutual Agreement Valuation of Work Done

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Bubble Engineering Company Ltd

Plaintiff

Maseno University

Defendant

Procedural Posture

Civil Suit / Ruling on Application for Judgment on Admission

  1. 1 Whether there was an express or implied admission by the defendant of the alleged indebtedness to the plaintiff.
  2. 2 Whether the plaintiff is entitled to judgment on admission under Order 13 Rule 2 of the Civil Procedure Code.
  3. 3 Whether the defendant's defence amounts to a mere denial insufficient to resist summary judgment.

Ratio Decidendi

The court found that the contract between the parties was not in dispute and that both parties mutually agreed to terminate it. A valuation was conducted by the Ministry of Public Works, which both parties accepted, and the defendant partially settled the amount due. The defendant's defence amounted to a mere denial without substantive challenge to the figures or the process. The court held that the documentary evidence and the defendant's conduct constituted an admission of indebtedness. Therefore, the requirements for judgment on admission under Order 13 Rule 2 of the Civil Procedure Code were satisfied, and the plaintiff was entitled to judgment for the balance claimed.

Court Disposition

application allowed; judgment entered for plaintiff

Orders

  • Judgment is entered for the plaintiff against the defendant for Kshs. 11,339,151/=
  • Plaintiff awarded costs and interest on the judgment sum