[2010] KEHC 98 (KLR)

[2010] KEHC 98 (KLR)

The court found that, despite the existence of a written contract, the conduct of the parties and their admissions established that certain extra works—such as additional socket units, Galana paving, verandah extension, and a water heating system—were carried out with the defendants' knowledge and consent, even if...

Source-derived case information.

Citation
[2010] KEHC 98 (KLR)
Parties
Plaintiff: Charles Muriungi t/a C.M. Steel Erectors & General Building Contractors; Defendant: Elizabeth Kuher-Heier; Defendant: Detlef Heier
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Suit 80 of 2001
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff in part; counterclaim by 1st defendant allowed in part; claim against 2nd defendant dismissed.
Legal Topics
Building Contracts, Variation of Contract, Parol Evidence Rule, Damages for Delay, Counterclaims, Quantum Meruit
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Variation of Contract Parol Evidence Rule Damages for Delay Counterclaims Quantum Meruit

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Charles Muriungi t/a C.M. Steel Erectors & General Building Contractors

Plaintiff

Elizabeth Kuher-Heier

Defendant

Detlef Heier

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there were extra works and materials carried out and supplied to the defendants in variance or in addition to the written contract.
  2. 2 Whether the plaintiff is entitled to payment for the purported extra work.
  3. 3 Which is the actual building plan or document the parties agreed on – Ex.1A or Ex.1B.

Ratio Decidendi

The court found that, despite the existence of a written contract, the conduct of the parties and their admissions established that certain extra works—such as additional socket units, Galana paving, verandah extension, and a water heating system—were carried out with the defendants' knowledge and consent, even if not formally documented. The court applied the exception to the parol evidence rule, admitting evidence of oral variations and conduct to supplement the written agreement. The court assessed the value of the extra works based on reasonable costs and awarded the plaintiff Kshs. 157,560 against the 1st defendant. However, the plaintiff was found to have breached the contract by...

Court Disposition

Judgment for the plaintiff in part; counterclaim by 1st defendant allowed in part; claim against 2nd defendant dismissed.

Orders

  • Judgment entered for the plaintiff against the 1st defendant for Kshs. 157,560.
  • Plaintiff's claim against the 2nd defendant dismissed with costs to the 2nd defendant.