[2014] KEHC 6522 (KLR)

[2014] KEHC 6522 (KLR)

The court determined that, given the nature of the dispute—specifically, the contested scope of works, payments made, and amounts outstanding—it is just and prudent to grant the prayer for appointment of a quantity surveyor. This will enable an independent assessment of the works and payments, which is central to...

Source-derived case information.

Citation
[2014] KEHC 6522 (KLR)
Parties
Plaintiff: Calbert Limited; Defendant: Sandstorm Investment Ltd; Defendant: Sandstorm Properties
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Case 25 of 2013
Procedural Posture
Civil Case / Ruling on Interlocutory Application (notice of Motion)
Outcome
Interlocutory application partially allowed; prayer for appointment of quantity surveyor granted; status quo to be maintained.
Judges
CW Meoli
Legal Topics
Breach of Contract, Scope of Works, Outstanding Payments
Source Language
en
Commercial and Corporate Breach of Contract Scope of Works Outstanding Payments

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Party arguments 2
Sign in to unlock

Parties

Calbert Limited

Plaintiff

Sandstorm Investment Ltd

Defendant

Sandstorm Properties

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Application (notice of Motion)

  1. 1 Whether there has been a breach of contract by either party.
  2. 2 Whether the scope of works contracted, works done, and amounts paid or outstanding are as claimed by the parties.

Ratio Decidendi

The court determined that, given the nature of the dispute—specifically, the contested scope of works, payments made, and amounts outstanding—it is just and prudent to grant the prayer for appointment of a quantity surveyor. This will enable an independent assessment of the works and payments, which is central to resolving the contractual dispute and any alleged breach. The court thus ordered the parties to agree on a quantity surveyor, whose report will inform further directions in the matter. The status quo is to be maintained pending the surveyor's report.

Court Disposition

Interlocutory application partially allowed; prayer for appointment of quantity surveyor granted; status quo to be maintained.

Orders

  • Prayer 5 of the Notice of Motion is granted: parties to agree upon a quantity surveyor to be enlisted.
  • Matter to be mentioned on 17th March, 2014 to receive the Surveyor’s Report and for directions.