[2012] KEHC 5275 (KLR)

[2012] KEHC 5275 (KLR)

The court found that the defendant breached its statutory duty under the Electric Power Act by failing to supply the agreed level of power and by not disconnecting supply when the plaintiff exceeded the contracted amount. However, the plaintiff failed to strictly prove its claim for special damages as required by...

Source-derived case information.

Citation
[2012] KEHC 5275 (KLR)
Parties
Plaintiff: Capital Fish K Ltd; Defendant: Kenya Power & Lighting Co. Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 369 of 1998
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiff succeeds on breach of statutory duty but claim for damages fails for lack of proof; judgment for defendant on damages; costs awarded to plaintiff.
Legal Topics
Breach of Contract, Supply of Goods and Services, Statutory Duties of Utilities, Special Damages, Negligence, Damages for Loss of Profits
Source Language
en
Commercial and Corporate Tort Law Breach of Contract Supply of Goods and Services Statutory Duties of Utilities Special Damages Negligence Damages for Loss of Profits

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Capital Fish K Ltd

Plaintiff

Kenya Power & Lighting Co. Ltd

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendant breached its statutory and contractual duty to supply the agreed level of power to the plaintiff.
  2. 2 Whether the defendant's failure to supply adequate power and suitable transformers constituted negligence resulting in damage to the plaintiff's equipment and business.
  3. 3 Whether the plaintiff is entitled to special or general damages for losses allegedly suffered due to power fluctuations and under-voltage.

Ratio Decidendi

The court found that the defendant breached its statutory duty under the Electric Power Act by failing to supply the agreed level of power and by not disconnecting supply when the plaintiff exceeded the contracted amount. However, the plaintiff failed to strictly prove its claim for special damages as required by law, as there was no documentary evidence such as receipts, invoices, or audited accounts to support the monetary claims for equipment damage, generator fuel, lost production, destroyed fish, or purchase of stabilizers. The court reaffirmed the principle that special damages must be specifically pleaded and proved, and that general damages are not awardable for breach of...

Court Disposition

Plaintiff succeeds on breach of statutory duty but claim for damages fails for lack of proof; judgment for defendant on damages; costs awarded to plaintiff.

Orders

  • Plaintiff's claim for special and general damages is dismissed for lack of proof.
  • Costs of the suit awarded to the plaintiff.