[2019] KEELC 1015 (KLR)

[2019] KEELC 1015 (KLR)

The court found that the plaintiff's application sought enforcement of a mutually agreed settlement between the parties regarding access to the plaintiff's properties. There was no opposition to the application, and the reliefs sought reflected the consensus reached by the parties. The court therefore granted the...

Source-derived case information.

Citation
[2019] KEELC 1015 (KLR)
Parties
Plaintiff: Central Auto Hardware Limited; Defendant: Kenya Urban Roads Authority; Defendant: Reynolds Construction Company; Defendant: Egis International
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 675 of 2017
Procedural Posture
Environment and Land Case / Ruling on Notice of Motion Dated 2/7/2019
Outcome
Application allowed; orders granted as prayed in prayers 1 and 2 of the notice of motion dated 2/7/2019; costs awarded to the plaintiff.
Judges
BM Eboso
Legal Topics
Road Construction Disputes, Access to Land, Injunctive Relief, Settlement Agreements
Source Language
en
Land and Property Civil Procedure Road Construction Disputes Access to Land Injunctive Relief Settlement Agreements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Central Auto Hardware Limited

Plaintiff

Kenya Urban Roads Authority

Defendant

Reynolds Construction Company

Defendant

Egis International

Defendant

Procedural Posture

Environment and Land Case / Ruling on Notice of Motion Dated 2/7/2019

  1. 1 Whether the defendants should be compelled to execute works as per the mutually agreed designs to ensure the plaintiff's properties are accessible.
  2. 2 Whether the plaintiff is entitled to costs of the application due to the defendants' failure to implement the settlement.

Ratio Decidendi

The court found that the plaintiff's application sought enforcement of a mutually agreed settlement between the parties regarding access to the plaintiff's properties. There was no opposition to the application, and the reliefs sought reflected the consensus reached by the parties. The court therefore granted the orders compelling the 1st defendant to execute the works as per the agreed designs within two months from the date of the ruling, and awarded costs to the plaintiff. The court clarified that the parties' decision to settle was voluntary and not pursuant to any court order.

Court Disposition

Application allowed; orders granted as prayed in prayers 1 and 2 of the notice of motion dated 2/7/2019; costs awarded to the plaintiff.

Orders

  • The 1st defendant by itself and/or its agents shall forthwith execute the works as per the designs agreed upon among all the parties so that the plaintiff’s properties may be accessible.
  • The 1st defendant by itself and/or its agents shall complete the said works within two (2) months from the date of this ruling.