[2016] KEELC 1157 (KLR)

[2016] KEELC 1157 (KLR)

The court found that the applicant failed to establish a prima facie case with a probability of success, as there was insufficient evidence linking the alleged damage to the respondent's quarry mining activities. The applicant did not provide any independent or impartial expert report to substantiate claims of...

Source-derived case information.

Citation
[2016] KEELC 1157 (KLR)
Parties
Applicant: Centurion Contractors & Agencies (K) Ltd; Respondent: Nyeri Concrete (K) Ltd
Court
Environment and Land Court
Court Station
Environment and Land Court at Nyeri
Jurisdiction
Kenya
Case Number
Environment & Land Case 250 of 2015
Procedural Posture
Miscellaneous Application / Ruling on Interlocutory Injunction
Outcome
application dismissed with costs to the respondent
Judges
L Waithaka
Legal Topics
Quarry Mining Operations, Temporary Injunctions, Nuisance, Environmental Licensing, Use of Explosives, Damage to Property
Source Language
en
Land and Property Environmental Law Quarry Mining Operations Temporary Injunctions Nuisance Environmental Licensing Use of Explosives Damage to Property

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2
Sign in to unlock

Parties

Centurion Contractors & Agencies (K) Ltd

Applicant

Nyeri Concrete (K) Ltd

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Interlocutory Injunction

  1. 1 Whether the respondent's quarry mining operations, including use of explosives, should be temporarily restrained pending determination of the suit.
  2. 2 Whether the applicant established a prima facie case with a probability of success for grant of a temporary injunction.
  3. 3 Whether the alleged damage to property and injury to livestock was sufficiently linked to the respondent's activities.

Ratio Decidendi

The court found that the applicant failed to establish a prima facie case with a probability of success, as there was insufficient evidence linking the alleged damage to the respondent's quarry mining activities. The applicant did not provide any independent or impartial expert report to substantiate claims of damage or danger posed by the respondent's use of explosives. The court also noted that both parties and their neighbors were engaged in similar quarry mining operations, making it difficult to characterize the respondent's activities as non-natural use of land. Furthermore, the applicant did not demonstrate that damages would not be an adequate remedy for any proven loss. The...

Court Disposition

application dismissed with costs to the respondent

Orders

  • The application dated 1st October, 2015 is dismissed with costs to the respondent.