[2014] KEHC 4114 (KLR)

[2014] KEHC 4114 (KLR)

The court found that although the arbitrator conducted multiple meetings and gave both parties opportunities to present their cases, he failed to address and determine all the issues referred to him, specifically those raised in paragraphs 5 and 6 of the applicant's memorandum of reply. These issues concerned the...

Source-derived case information.

Citation
[2014] KEHC 4114 (KLR)
Parties
Applicant: Centurion Engineers & Builders Ltd.; Respondent: Kenya Bureau of Standards
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 506 of 2012
Procedural Posture
Miscellaneous Application / Ruling on Application to Set Aside Arbitral Award
Outcome
Application allowed; arbitral award set aside and matter referred back to arbitrator for determination of outstanding issues; no order as to costs.
Judges
JB Havelock
Legal Topics
Arbitration Award Setting Aside, Contract Variations, Construction Contracts, Procedural Fairness, Scope of Reference
Source Language
en
Alternative Dispute Resolution Commercial and Corporate Arbitration Award Setting Aside Contract Variations Construction Contracts Procedural Fairness Scope of Reference

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Centurion Engineers & Builders Ltd.

Applicant

Kenya Bureau of Standards

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application to Set Aside Arbitral Award

  1. 1 Whether the arbitrator failed to address all issues referred to him, particularly those in paragraphs 5 and 6 of the applicant's memorandum of reply.
  2. 2 Whether the arbitral award should be set aside under section 35(2)(a)(iv) of the Arbitration Act for exceeding or failing to address the scope of reference.
  3. 3 Whether the applicant was denied a fair hearing during the arbitral proceedings.

Ratio Decidendi

The court found that although the arbitrator conducted multiple meetings and gave both parties opportunities to present their cases, he failed to address and determine all the issues referred to him, specifically those raised in paragraphs 5 and 6 of the applicant's memorandum of reply. These issues concerned the validity of contract variations, compliance with contractual procedures, and alleged collusion between the contractor and architect. The arbitrator confined his determination to unpaid certificates, interest, and losses, without considering the broader disputes. The court held that this omission amounted to a failure to address the full scope of the reference, thus meeting the...

Court Disposition

Application allowed; arbitral award set aside and matter referred back to arbitrator for determination of outstanding issues; no order as to costs.

Orders

  • The arbitral award dated 28th November 2013 is set aside.
  • The matter is referred back to the arbitrator to consider and determine the issues raised in paragraphs 5 and 6 of the applicant's memorandum of reply dated 13th August 2013.