[2005] KEHC 812 (KLR)

[2005] KEHC 812 (KLR)

The court found that the defendant had obtained all necessary approvals from the Nairobi City Council for the construction of a maisonette on the suit plot, and that the construction complied with the lease terms and applicable by-laws, including plot coverage restrictions. The plaintiffs failed to prove that the...

Source-derived case information.

Citation
[2005] KEHC 812 (KLR)
Parties
Plaintiff: Chairman Rahmat Ghassim (suing on behalf of Nyari Residents Welfare Society); Defendant: Sadhu Singh Devgun
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 803 of 2000
Procedural Posture
Civil Suit / Judgment
Outcome
plaintiff's suit dismissed with costs to the defendant
Judges
JB Ojwang
Legal Topics
Land Use Restrictions, Injunctions, Building by Laws, Property Development, Approval of Building Plans
Source Language
en
Land and Property Civil Procedure Land Use Restrictions Injunctions Building by Laws Property Development Approval of Building Plans

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Chairman Rahmat Ghassim (suing on behalf of Nyari Residents Welfare Society)

Plaintiff

Sadhu Singh Devgun

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendant's construction of a residential maisonette on plot L.R No. NAIROBI/BLOCK 94/226 is unlawful and in breach of the lease and City Council by-laws.
  2. 2 Whether the plaintiff society stands to suffer irreparable loss as a result of the defendant's construction.
  3. 3 Whether the City Council's approval of the defendant's building plans was valid and binding.

Ratio Decidendi

The court found that the defendant had obtained all necessary approvals from the Nairobi City Council for the construction of a maisonette on the suit plot, and that the construction complied with the lease terms and applicable by-laws, including plot coverage restrictions. The plaintiffs failed to prove that the defendant's actions were unlawful or that the construction would cause irreparable loss or depreciation of property values. The City Council, as the approving authority, was not made a party to the suit, and no evidence was adduced to show that its approval was invalid. The court held that the equitable remedy of injunction was not available as the construction was already...

Court Disposition

plaintiff's suit dismissed with costs to the defendant

Orders

  • The plaintiffs' prayer for a permanent injunction restraining the defendant from constructing a residential house on plot L.R No. NAIROBI/BLOCK 94/226 is dismissed.
  • The plaintiffs shall bear the defendant's costs in this suit.