[2024] KEHC 12055 (KLR)
The court found that the applicant had established a prima facie case warranting the grant of leave to apply for orders of certiorari and prohibition against the decision of the Public Procurement Administrative Review Board and the 2nd Respondent's Notice of Intention to Award contract. The court further exercised...
Source-derived case information.
- Citation
- [2024] KEHC 12055 (KLR)
- Parties
- Applicant: Chakra Company Limited; Respondent: Public Procurement Administrative Review Board; Respondent: Agro Chemical & Food Company Limited
- Court
- High Court
- Court Station
- High Court at Kisumu
- Jurisdiction
- Kenya
- Case Number
- Judicial Review E009 of 2024
- Procedural Posture
- Judicial Review / Leave Application Ruling
- Outcome
- Leave to apply for judicial review granted; leave to operate as stay of implementation of impugned decision and notice; directions for service and filing of substantive application.
- Judges
- MS Shariff
- Legal Topics
- Public Procurement Review, Judicial Review Leave, Certiorari and Prohibition, Stay of Implementation
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Chakra Company Limited
Applicant
Public Procurement Administrative Review Board
Respondent
Agro Chemical & Food Company Limited
Respondent
Procedural Posture
Judicial Review / Leave Application Ruling
Legal Issues
- 1 Whether the applicant has established a prima facie case to warrant grant of leave to apply for orders of certiorari and prohibition.
- 2 Whether leave should operate as a stay of the implementation of the impugned decision and notice of intention to award contract.
Ratio Decidendi
The court found that the applicant had established a prima facie case warranting the grant of leave to apply for orders of certiorari and prohibition against the decision of the Public Procurement Administrative Review Board and the 2nd Respondent's Notice of Intention to Award contract. The court further exercised its discretion to order that the leave granted would operate as a stay of the implementation of the impugned decision and notice, in order to preserve the status quo pending the hearing and determination of the substantive judicial review application. The court directed the applicant to serve the application and supporting documents on the respondents simultaneously with the...
Court Disposition
Leave to apply for judicial review granted; leave to operate as stay of implementation of impugned decision and notice; directions for service and filing of substantive application.
Orders
- Leave is granted to the ex parte applicant to apply for orders of certiorari and prohibition in terms of prayers Nos. 2 – 4 of the chamber summons within 21 days from the date hereof.
- This leave shall operate as a stay of the implementation of the decision of the Public Procurement Administrative Review Board dated 20th September, 2024 in application No. 85 of 2024 and of the 2nd Respondent’s Notice of Intention to Award contract transmitted to the Applicant on 25th September, 2024.
Full Case Text
Judgment text and source record
18 paragraphs
Chakra Company Limited v Public Procurement Administrative Review Board & another (Judicial Review E009 of 2024) [2024] KEHC 12055 (KLR) (7 October 2024) (Ruling)
Neutral citation: [2024] KEHC 12055 (KLR)
Republic of Kenya
In the High Court at Kisumu
Judicial Review E009 of 2024
MS Shariff, J
October 7, 2024
Between
Chakra Company Limited
Applicant
and
Public Procurement Administrative Review Board
1st Respondent
Agro Chemical & Food Company Limited
2nd Respondent
Ruling
1. Upon perusal of the chamber summons dated 3. 10. 24, the statement of facts of even date, the amended statement of facts and the verifying affidavit I do hereby allow the application and? Make the following orders:-1. The ex parte applicant is hereby granted leave to apply for orders of certiorari and prohibition in terms of prayers Nos. 2 – 4 of the chamber summons within 21 days from the date hereof.2. This leave shall operate as a stay of the implementation of the decision of the Public Procurement Administrative Review Board dated 20th September, 2024 in application No. 85 of 2024 and of the 2nd Respondent’s Notice of Intention to Award contract transmitted to the Applicant on 25. 9.2024. 3.The ex parte Applicant is directed to serve this application, statement of facts, amended statement and verifying affidavit upon the Respondent simultaneously with the substantive application.
DATED, SIGNED AND DELIVERED THIS 7THDAY OF OCTOBER, 2024. M. S. SHARIFFJUDGE