The court found that the appellant had demonstrated the risk of substantial loss if the decretal sum was released to the respondent, as the respondent's ability to refund the sum was doubtful. The application for stay was filed promptly after judgment, satisfying the requirement of timeliness. Although the appellant...

Source-derived case information.

Citation
[2017] KEHC 6687 (KLR)
Parties
Appellant: Channa Construction Company Limited; Respondent: Joshua Ndakalu Mukuna
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Appeal 243 of 2016
Procedural Posture
Civil Appeal / Ruling on Stay of Execution Pending Appeal
Outcome
Application for stay of execution granted on condition.
Judges
JK Sergon
Legal Topics
Stay of Execution, Security for Due Performance, Substantial Loss, Timeliness of Application, Workplace Injury, Compensatory Damages
Source Language
en
Civil Procedure Employment and Labour Stay of Execution Security for Due Performance Substantial Loss Timeliness of Application Workplace Injury Compensatory Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Channa Construction Company Limited

Appellant

Joshua Ndakalu Mukuna

Respondent

Procedural Posture

Civil Appeal / Ruling on Stay of Execution Pending Appeal

  1. 1 Whether the appellant has demonstrated substantial loss if stay of execution is not granted.
  2. 2 Whether the application for stay of execution was filed without unreasonable delay.
  3. 3 What form of security should be provided for due performance of the decree.

Ratio Decidendi

The court found that the appellant had demonstrated the risk of substantial loss if the decretal sum was released to the respondent, as the respondent's ability to refund the sum was doubtful. The application for stay was filed promptly after judgment, satisfying the requirement of timeliness. Although the appellant did not propose a form of security, the court exercised its discretion to require the appellant to deposit the decretal sum in a joint interest-earning account as security for the due performance of the decree. The stay of execution was therefore granted on this condition.

Court Disposition

Application for stay of execution granted on condition.

Orders

  • Order for stay of execution granted on condition that the decretal sum of Ksh.1,287,513/- be deposited in an interest earning account in the joint names of advocates for both parties within 30 days.