[2014] KEELC 382 (KLR)

[2014] KEELC 382 (KLR)

The court found that while both the Plaintiff and 3rd Defendant are the lawful owners of their respective parcels, the Plaintiff failed to establish a clear prima facie case for a temporary injunction to halt construction, as the 3rd Defendant had obtained approvals and the construction was nearly complete. However,...

Source-derived case information.

Citation
[2014] KEELC 382 (KLR)
Parties
Plaintiff: Charles Jonyo Osicho; Defendant: City Council of Nairobi; Defendant: Kenya Building Society Ltd; Defendant: Jared Mbugua Ragoi
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
? 717 of 2013
Procedural Posture
Environment and Land Suit / Ruling on Interlocutory Injunction Application
Outcome
Interlocutory injunction granted in part; status quo orders issued pending determination of the suit.
Judges
P Nyamweya
Legal Topics
Temporary Injunctions, Change of User, Environmental Impact Assessment, Trespass, Land Use Planning, Zoning
Source Language
en
Land and Property Environmental Law Civil Procedure Temporary Injunctions Change of User Environmental Impact Assessment Trespass Land Use Planning +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 9 Party arguments 2
Sign in to unlock

Parties

Charles Jonyo Osicho

Plaintiff

City Council of Nairobi

Defendant

Kenya Building Society Ltd

Defendant

Jared Mbugua Ragoi

Defendant

Procedural Posture

Environment and Land Suit / Ruling on Interlocutory Injunction Application

  1. 1 Whether the Plaintiff has established a prima facie case for grant of a temporary injunction against the Defendants.
  2. 2 Whether the 3rd Defendant's construction and intended use of Nairobi Block 121/208 is lawful and compliant with planning and environmental laws.
  3. 3 Whether the Plaintiff will suffer irreparable harm if the injunction is not granted.

Ratio Decidendi

The court found that while both the Plaintiff and 3rd Defendant are the lawful owners of their respective parcels, the Plaintiff failed to establish a clear prima facie case for a temporary injunction to halt construction, as the 3rd Defendant had obtained approvals and the construction was nearly complete. However, the court noted unresolved contradictions regarding the approved use of the 3rd Defendant's property, the absence of clear evidence of a lawful change of user, and the lack of an environmental impact assessment despite the development being out of character with the surrounding residential area. The court held that the balance of convenience required maintaining the status...

Court Disposition

Interlocutory injunction granted in part; status quo orders issued pending determination of the suit.

Orders

  • The 3rd Defendant, his agents and/or servants are restrained from using the premises constructed on Title No. Nairobi Block 121/208 or any part thereof as a shop or carrying out any trade and business thereon, pending the hearing and determination of the suit or until further orders.
  • The Plaintiff, his agents and/or servants are restrained from demolishing or in any other manner howsoever interfering with the 3rd Defendant’s premises constructed on Nairobi Block 121/208 or any part thereof, pending hearing and determination of this suit or until further orders.