[2010] KEHC 97 (KLR)

[2010] KEHC 97 (KLR)

The court found that, while the written contract governed the main terms, the conduct of the parties and their admissions established that certain extra works—such as additional socket units, Galana pavement, and increased verandah and main house measurements—were carried out with the defendants' knowledge and...

Source-derived case information.

Citation
[2010] KEHC 97 (KLR)
Parties
Plaintiff: Charles Muriungi t/a C.M. Steel Erectors & General Building Contractors; Defendant: Elizabeth Kuher-Heier; Defendant: Detlef Heier
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Suit 80 of 2001
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff against the 1st defendant for Kshs. 157,560; judgment for the 1st defendant on the counterclaim for Kshs. 20,000; claim against the 2nd defendant dismissed with costs.
Legal Topics
Building Contracts, Variation of Contract, Parol Evidence Rule, Breach of Contract, Damages Assessment
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Variation of Contract Parol Evidence Rule Breach of Contract Damages Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Charles Muriungi t/a C.M. Steel Erectors & General Building Contractors

Plaintiff

Elizabeth Kuher-Heier

Defendant

Detlef Heier

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there were extra works and materials carried out and supplied to the defendants in variance or in addition to the written contract.
  2. 2 Whether the plaintiff is entitled to payment for the purported extra work.
  3. 3 Which is the actual building plan or document the parties agreed on—Ex.1A or Ex.1B.

Ratio Decidendi

The court found that, while the written contract governed the main terms, the conduct of the parties and their admissions established that certain extra works—such as additional socket units, Galana pavement, and increased verandah and main house measurements—were carried out with the defendants' knowledge and consent, even if not formally documented. The court applied the exception to the parol evidence rule, admitting extrinsic evidence to establish that the written contract did not represent the entire agreement. The court assessed the value of the extra works based on reasonable estimates and awarded the plaintiff Kshs. 157,560 against the 1st defendant. However, the plaintiff was...

Court Disposition

Judgment for the plaintiff against the 1st defendant for Kshs. 157,560; judgment for the 1st defendant on the counterclaim for Kshs. 20,000; claim against the 2nd defendant dismissed with costs.

Orders

  • Plaintiff awarded Kshs. 157,560 against the 1st defendant for extra works.
  • 1st defendant awarded Kshs. 20,000 general damages for breach of contract due to delay.