[2017] KEHC 559 (KLR)

[2017] KEHC 559 (KLR)

The court found that the plaintiff and defendants entered into a construction contract with a total value of KES 8,485,000, including admitted variations. The plaintiff was paid KES 6,315,000, leaving a balance of KES 2,170,000, which was consistently claimed and acknowledged in correspondence. The plaintiff's...

Source-derived case information.

Citation
[2017] KEHC 559 (KLR)
Parties
Plaintiff: Charles Muriungi (Trading as C.M. Steel Erectors and General Building Contractors); Defendant: Mercy Wanjiru Gachongo; Defendant: Pisgah Limited; Defendant: Engineer Ezio Dubimi
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Case 88 of 2006
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiff awarded KES 2,170,000 as balance of contractual sum; claim for security charges dismissed; counterclaim dismissed.
Judges
SJ Chitembwe, CC Kipkorir
Legal Topics
Building Contracts, Contractual Disputes, Quantum of Damages, Specific Performance
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Contractual Disputes Quantum of Damages Specific Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Charles Muriungi (Trading as C.M. Steel Erectors and General Building Contractors)

Plaintiff

Mercy Wanjiru Gachongo

Defendant

Pisgah Limited

Defendant

Engineer Ezio Dubimi

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff is entitled to the balance of the contractual sum claimed in the plaint dated 17/10/2006.
  2. 2 Whether the plaintiff is entitled to monthly security charges from 1/9/2006.
  3. 3 Whether the defendants have proved their counterclaim for general damages and loss of user.

Ratio Decidendi

The court found that the plaintiff and defendants entered into a construction contract with a total value of KES 8,485,000, including admitted variations. The plaintiff was paid KES 6,315,000, leaving a balance of KES 2,170,000, which was consistently claimed and acknowledged in correspondence. The plaintiff's refusal to hand over the property to the 1st defendant was not justified by evidence, but did not extinguish his right to the contractual balance. However, the claim for monthly security charges was denied because the plaintiff unlawfully retained possession and benefited from the property for over ten years. The court also denied the counterclaim for damages, finding insufficient...

Court Disposition

Plaintiff awarded KES 2,170,000 as balance of contractual sum; claim for security charges dismissed; counterclaim dismissed.

Orders

  • Plaintiff is awarded KES 2,170,000 as the balance of the contractual sum.
  • The awarded amount shall attract interest only after the delivery of this judgment, not for the period of prior occupation.