[2019] KEHC 4810 (KLR)

[2019] KEHC 4810 (KLR)

The court found that while there was a valid contract between the parties and the appellant breached the contract by failing to provide the stipulated seven-day notice prior to termination, the trial court erred in awarding general damages and payment in lieu of notice. The law is clear that general damages are not...

Source-derived case information.

Citation
[2019] KEHC 4810 (KLR)
Parties
Appellant: China Overseas Engineering Company Limited; Respondent: Isaaq Kichwen Kijo
Court
High Court
Court Station
High Court at Kakamega
Jurisdiction
Kenya
Case Number
Civil Appeal 123 of 2017
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal_allowed
Judges
DN Musyoka
Legal Topics
Breach of Contract, Damages for Breach, Termination of Contract, Pleading and Proof of Special Damages
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Damages for Breach Termination of Contract Pleading and Proof of Special Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

China Overseas Engineering Company Limited

Appellant

Isaaq Kichwen Kijo

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether there was a valid contract between the parties.
  2. 2 Whether the contract was breached and by whom.
  3. 3 Whether the respondent was entitled to damages for breach of contract, and if so, what type of damages.

Ratio Decidendi

The court found that while there was a valid contract between the parties and the appellant breached the contract by failing to provide the stipulated seven-day notice prior to termination, the trial court erred in awarding general damages and payment in lieu of notice. The law is clear that general damages are not available for breach of contract; only special damages, which must be specifically pleaded and proved, can be awarded. In this case, the respondent neither pleaded nor proved any special damages, nor did he plead for payment in lieu of notice. Therefore, the awards made by the trial court were not justified in law. The only remedy available to the respondent would have been...

Court Disposition

appeal_allowed

Orders

  • The award of general damages by the trial court is set aside.
  • The award of payment in lieu of three months' notice is set aside.